section 317 of the Housing and Regeneration Act 2008. Section 317 amends section

#

Source page 1

To:

The Chief Executive Unitary, Metropolitan, District and London Borough Councils in England County and County Borough Councils in Wales

The Town Clerk, City of London The Clerk, Council of the Isles of Scilly The Sub-Treasurer, Inner Temple The Under Treasurer, Middle Temple

The Head of Building Control Unitary Metropolitan, District and London Borough Councils in England County and County Borough Councils in Wales City of London Council of the Isles of Scilly

Approved Inspectors

cc:The Chief Executive: County Councils in England National Park Authorities in England & Wales

The Chief Fire Officer: Fire Authorities in England and Wales

9September 2008

Our ref: CI/43/19/1

Dear Sir or Madam

Housing and Regeneration Act 2008 section 317: time limit for prosecutions of breaches of building regulations

I am writing to inform you about the commencement on 22 September 2008 of

section 317 of the Housing and Regeneration Act 2008. Section 317 amends section

35A of the Building Act 1984 (“the Act”) so that the time limit for bringing prosecutions for all breaches of building regulations which are subject to prosecution under section 35 of the Act is extended to two years from the completion of the offending building work. The two year limit is subject to a requirement that any prosecution must be brought within six months of the date on which a local authority Department of Communities and Local Government Tel 0207 944 5720 Sustainable Buildings, Zone 2/H6 Fax 0207 944 5719 Eland House, Bressenden Place Email : jessica.matthew@communities.gsi.gov.uk

Page 2

#

Source page 2

has sufficient evidence to justify bringing a prosecution. The extension of the time limit is not retrospective, i.e. it applies only to offences committed on or after 22 September 2008.

You may recall that we wrote to you on 20 March about the Building (Amendment) Regulations 2008 (S.I. 2008/671), which included the addition of regulation 22A to the Building Regulations. Regulation 22A designated certain provisions of building regulations for which the time limit for bringing prosecutions for breaches had been extended to two years for offences committed on or after 6 April 2008. This two year limit is also subject to the requirement that any prosecution must be brought within six months of the date on which a local authority has sufficient evidence to justify bringing a prosecution. The provisions designated by new regulation 22A were regulations 4 and 6, to the extent that Part L of Schedule 1 imposes a requirement, and regulations 4A, 4B, 17C and 17D.

The amendment of section 35A of the Act by section 317 of the Housing and Regeneration Act means that all offences under section 35 of the Act committed on or after 22 September 2008 will be subject to the extended time limit for bringing prosecutions. Until that date the extended time limit only applies to offences committed on or after 6 April 2008 in relation to the provisions designated by regulation 22A. Regulation 22A will for the time being continue in force, although we intend to revoke it as soon as possible after 22 September, as after that date it will no longer be necessary. Please note that even after regulation 22A is revoked the extended time limit for bringing prosecutions for any offences committed in relation to the designated provisions between 6 April and 22 September 2008 will continue to apply.

The following table may help to explain the effect of these changes in practice:

Date of offence under section 35Provisions to which section 35 applies breachedTime limit for bringing prosecution
Before 6 April 2008All provisionsSix months
6 April 2008 to 21 September 2008Provisions designated by regulation 22ATwo years, subject to maximum of 6 months from date of obtaining sufficient evidence to bring prosecution
6 April 2008 to 21 September 2008Provisions not designated by regulation 22ASix months
From 22 September 2008All provisionsTwo years, subject to maximum of 6 months from date of obtaining sufficient evidence to bring prosecution

Page 3

#

Source page 3

Enquiries

Any enquiries on this Circular Letter should be addressed to Ian Drummond, Sustainable Buildings Division, Department for Communities and Local Government, Zone 2/H6, Eland House, Bressenden Place, London SW1E 5DU (Tel: 020 7944 4821, e-mail: ian1.drummond@communities.gsi.gov.uk).

Yours faithfully

Diagram on page 3

JESSICA MATTHEW

Deputy Director

Sustainable Buildings Division

Your next step

Meet your mini assistant.

Sign up to ask questions about Building Regulations and explore the guidance with Avoice.

Sign up

Already have an account? Log in

Already an Avoice customer? Log in