Purpose

#

Source page 1

A safety case report sets out the building safety risks of a high-rise residential building and how they are being managed.

A high-rise residential building has at least:

7 storeys or is at least 18 metres high

2 residential units

Building safety risks are the risk of:

the spread of fire or smoke in the building

structural failure of the building

The building must be registered with the Building Safety Regulator (BSR) before people live there. These buildings are known as higher-risk buildings under the Building Safety Act 2022

When you need a safety case report

#

Source page 2

As the principal accountable person (PAP), you should prepare the safety case report as soon as possible when:

the building is already occupied or becomes occupied

you become the PAP

You must send BSR a copy of your safety case report:

when BSR tells you to apply for a building assessment certificate

at any time when BSR asks you for it

To help identify the latest version of your report, include a date, or version number, or both.

Basic building information

#

Source page 3

In your safety case report include the building’s:

name, if it has one

full postal address

registration number, this begins with ‘HRB’ and is quoted when BSR contacts you

build date

height

number of storeys above ground level

floorplans for each type of storey layout

location, using a map or photo, or both

You should also describe the:

number and type of residential units, like flats or maisonettes

common parts, for example community room, bin store, underground parking

resident profile, for example if any residents need help to evacuate or have additional needs, this should be the same as in your resident engagement strategy

other building uses which are not residential

surrounding area

services and utilities provided to the building, including isolation points

if the building is supplied with gas, include whether gas is supplied to individual flats and, if so, piping routes

Changes of use

If the building has changed use since its original construction, include this in your safety case report. For each change of use describe:

what the change of use is

when the change of use happened

how the change is relevant to building safety risks

the loading design limits of the building and how to prevent overloading

Multi-building developments

If the building is one of a number of structures, include a description of the wider development. This should include any shared facilities such as plant rooms and parking.

Missing information

If you have not found all the information about the building you need, you should explain in your report what you did to try and find it.

People responsible for the building

#

Source page 4

You should include in your report the name and phone number or email address of:

the PAP

the building owner, if this is not the PAP

any other accountable persons (APs) for the building

any responsible persons under the Regulatory Reform (Fire Safety) Order 2005 (the ‘Fire Safety Order’)

any managing agents for the building

Include details about how the APs share relevant information with each other and with you.

If you or another AP is a resident management company and has appointed a building safety director, include details of the building safety director.

Construction methods and materials

#

Source page 5

Your report should contain the main structural elements of the building, such as:

materials of construction, be clear about where different materials are used in different parts of the building

construction methods used, for example, large panel system

the primary load bearing methods, for example, pre-cast planks on a steel frame

stability, for example, concrete shear walls

secondary systems relevant to building safety risks, for example, cladding support systems

materials used in other elements, for example, facade, wall attachment, roofing, basement or underground levels

foundations and local ground conditions such as flood risk and underground tunnels

Structural condition of the building

#

Source page 6

Your report should contain any history of structural problems with the building, describe:

the structural problems, and how the problems were identified

the actions taken to investigate them

any remedial measures taken

Set out how you make sure that the building stays structurally sound. For a building:

more than 3 years old, explain what arrangements are in place

less than 3 years old, explain what you plan to do to manage the structure in the future

Structural surveys and inspections

If any surveys or inspections have been carried out to assess the current structural condition of the building, include:

the type and scope of the structural surveys or inspections

the methods used, such as visual or invasive

who carried them out

why the approach was taken

the findings

If the survey or inspection was done:

in-house, explain how you made sure the people involved were competent to carry out the survey or inspection

by a third party, explain how you selected them and checked their competence to work on high-rise residential buildings

Include a summary of the findings and any recommended actions. Include details about actions that:

have been completed, and when they were completed

have not yet been completed, including timescales for completion and any temporary measures put in place to mitigate risks

have not been acted upon and explain why

Include details about how you keep up to date with structural developments, such as signing up for safety alerts.

Information about the structural condition of the building should be included in the building safety risk assessments.

Building work, refurbishment and remediation

#

Source page 7

Include a summary of any building work, refurbishment or remediation since original construction that could have affected building safety risks. State the year the work was completed.

Large panel system (LPS) buildings

For LPS buildings, state whether remediation has been carried out since the Ronan Point collapse in 1968. Include a summary of the remediation work, and if there are:

records of the work, state if there were any sample checks verifying the work

no records of the work, set out how the building’s structural condition has been determined

If the building has not been remediated, set out the measures taken to prevent structural failure because of LPS weaknesses.

Building work in progress or planned

If building work is in progress, or is planned to take place, your report should include:

a description of the work

when the work is expected to be completed

the steps taken to manage building safety risks until the work is complete

Fire safety measures

#

Source page 8

In your report, state how you know what the building’s fire safety standards are, for example:

you know the standards the building was built to

you’ve inferred the standards based on factors such as build date, height and type of building

the building was constructed using a fire-engineered solution, based on design and agreement with a fire engineer

Describe the building’s main features relevant to the spread of fire, including:

external wall systems

structural fire protection, such as cladding or fire-resistant coatings

prevention and protection measures to manage the risk of fire spread, such as smoke control systems, sprinklers and alarms

If the building has balconies, describe their:

type, for example Juliet, cantilever, hung, stacked, internal

attachment methods

structural and decorative materials

dimensions

Include a summary of any:

incidents involving spread of fire, including any reported to BSR and recorded on your mandatory occurrence reporting system

enforcement action relevant to spread of fire under the Fire Safety Order, or by BSR

Compartmentation

Provide information about the compartmentation in the building including:

firefighting shafts including lift shafts and wells

fire resistance between floors

compartmentation between the basement, if there is one, and the ground floor

compartmentation between individual residential units and other areas such as bin stores, plant rooms and car parks

fire resistance between residential corridors and flats, between flats, above false ceilings

penetrations into residential units such as services and utilities, for example water pipes, gas pipes and electrical cables

where the building is mixed-use, compartmentation between residential and non-residential parts of the building

Describe the building’s compartmentation standards, such as for floors, walls, shafts, and load bearing elements.

Explain how you manage any maintenance, or work of third parties, that could affect compartmentation.

Fire doors

You should show that fire doors are in place in necessary locations, such as entrance doors to flats, stairs and lobbies.

If you or any other AP carries out a fire door survey, include the:

competence of the surveyor

the survey’s significant findings, including the AP’s response

Provide evidence that fire doors and door closers are regularly inspected to ensure they work properly and remain in good condition.

Methods of smoke control

Describe the methods of smoke control in the building. These could include:

natural smoke control systems

mechanical smoke ventilation systems

pressure differential systems

Escape routes

Describe the number of escape routes, along with travel distances and any dead ends.

Stairs

Provide information about the staircases in the building, including:

the number of staircases

if they are firefighting or escape stairs, and if they are internal or external

if they serve all floors and flats, or just some

if they serve areas shared with other blocks such as basements and car parks

the width, including whether the width changes

Detection and warning systems

Include details of any fire detection and warning systems.

Sprinklers or other suppression systems

Describe any suppression systems, such as their:

locations and coverage

specifications, such as activation temperature, maintenance and testing requirements

water supply

power supply

Building safety risk assessments

#

Source page 9

Your report should contain a summary of the building safety risk assessments carried out by each AP.

You can read the guidance about assessing building safety risks. It tells you what APs should cover in a building safety risk assessment and how to carry them out.

Describe how the risk assessments were carried out

Include in your report:

the risk assessment processes used to identify building safety risks, such as HAZID or bow tie

who was involved in the risk assessments, their competence and their specialist expertise

Describe the findings and recommendations

Include a summary of the significant findings and recommended actions from the risk assessments.

Include a description of the:

possible safety risk scenarios identified by each AP

likelihood of each scenario happening

consequences of each scenario if it did happen

Describe how building safety risks are managed

Your report should describe:

what each AP is doing to manage building safety risks

how each AP is taking all reasonable steps to manage the building safety risks in their parts of the building

Include details about the recommended actions following the risk assessments that have:

been completed, and when they were completed

not yet been completed, state when they will be completed and what you have done to keep risks under control until the recommendations can be met

not been acted upon and explain why

The summary of the building’s safety management systems should describe how actions to manage risks are tracked and completed properly and on time.

Emergency plan

#

Source page 10

Set out the emergency plan in place for the building, including:

the evacuation strategy

how the emergency plan has been communicated to residents

how residents needs have been taken into account, for example, if any residents need help to evacuate or have any additional needs

how residents should respond to emergency situations

You can read guidance about reducing the severity of an incident if one occurs. It tells you more about evacuation strategies and how to communicate them to residents.

If the current evacuation strategy is different to the original design intent of the building, include an explanation of each change and the reason for that change.

Fire and emergency services

Provide details of the facilities for use by the fire service, including:

firefighting shafts and any firefighting lifts

risers and fire mains including type

hydrant locations

fire service vehicle access

site drawings

Include a description of the information shared with the emergency services to support their emergency planning. To understand more about this read the guidance about the information APs must share with the fire and rescue authority.

Review the plan

Include how you will review the emergency arrangements in place to make sure they remain effective. This should include scheduling regular testing and maintenance checks.

Safety management systems

#

Source page 11

Include a summary of the safety management systems in place that APs are using to manage building safety risks.

Continuous improvement

In your safety case report, include a statement which confirms your commitment to continually improve the management of building safety risks. If you have one, you can also include an action or improvement plan that demonstrates how you plan to improve building safety.

Roles and responsibilities

Describe the main building safety management roles, such as fire safety manager, and include:

who currently carries out those roles

their responsibilities

how their competence has been checked and what you do to make sure their competence stays up to date

Maintenance and inspection work

Describe how you maintain and inspect the building, giving specific examples and schedules, for managing:

routine maintenance work

inspections of the building and the physical controls in place that manage building safety risks, (include controls that are only used occasionally, such as controls that operate automatically if a fire alarm is triggered)

the progress of fixing issues that are identified by maintenance or inspections

Describe how urgent or emergency work is managed, which includes breakdowns, damage or actions identified by other inspections.

Describe the systems that you, and other APs for the building, use to assure the:

competence of designers and contractors that work on the buildings

quality of materials used

how the building safety risks are assessed and kept under control while works are being done

Managing changes

Describe how you make sure that building safety is protected when you make changes:

in the building

to how the building is managed

to how your organisation is managed

Include:

the type of changes that you will manage

how you will check and assess how changes might affect building safety risks, both during and after the change is completed

how you will make sure that controls are put back once a change has been completed

how you will make sure the change has been completed as intended

Monitoring performance

Include evidence that demonstrates how you monitor the management of building safety risks. Describe:

one or more examples of what you monitor, and how you assess performance

what you would do if performance goes down

how performance information is reported to senior managers

Reviewing safety management systems

Describe how and when the:

effectiveness of each system is reviewed

how you make sure any changes to each system are implemented

Updating your safety case report

#

Source page 12

You should update your safety case report, for example, when:

improvement work is carried out to manage building safety risks

work on the building impacts building safety risks

Tell BSR about changes to your report

You must tell BSR as soon as possible if you update your safety case report to include:

new or increased building safety risks that have been identified

further measures taken to manage risks

BSR will ask you for:

the date the update to the safety case report was made

a brief description of the update

the reason for making the update

BSR may ask you to provide the updated safety case report. There is a charge you will need to pay if BSR decides to review the updated safety case report. This is set out in the BSR charging scheme.

Your next step

Meet your mini assistant.

Sign up to ask questions about Building Regulations and explore the guidance with Avoice.

Sign up

Already have an account? Log in

Already an Avoice customer? Log in