| To: The Chief Executive Unitary, Metropolitan, District and London Borough Councils in England County and County Borough Councils in Wales The Town Clerk, City of London The Clerk, Council of the Isles of Scilly The Sub-Treasurer, Inner Temple The Under Treasurer, Middle Temple The Head of Building Control Unitary Metropolitan, District and London Borough Councils in England County and County Borough Councils in Wales City of London Council of the Isles of Scilly Approved Inspectors cc: The Chief Executive: County Councils in England National Park Authorities in England & Wales The Chief Fire Officer: Fire Authorities in England and Wales |
28September 2010
Dear Sir/Madam
Building Regulations 2010
Building (Approved Inspectors etc) Regulations 2010
As mentioned in our Circular Letter of 18 March 2010, I am now writing to inform you about the publication of the Approved Documents and compliance guides to support
Page 2
#Source page 2
the changes made to Parts F and J of Schedule 1 to, and the energy efficiency requirements of, the Building Regulations 2000 and the Building (Approved Inspectors etc) Regulations 2000 by the Building and Approved Inspectors (Amendment) Regulations 2010 (SI 2010/719). These changes are now consolidated within the Building Regulations 2010 (SI 2010/2214) and the Building (Approved Inspectors etc) Regulations 2010 (SI 2010/2215).
Publications
Approved Document F:Ventilation (2010)
Approved Document J:Combustion appliances and fuel storage systems (2010)
Approved Document L1A:Conservation of fuel and power – New dwellings (2010)
Approved Document L1B Conservation of fuel and power – Existing dwellings (2010)
Approved Document L2A:Conservation of fuel and power – New buildings other than dwellings (2010)
Approved Document L2B:Conservation of fuel and power – Existing dwellings other than dwellings (2010)
Domestic Ventilation Compliance Guide (2010)
Domestic Building Services Compliance Guide (2010)
Non-domestic Building Services Compliance Guide (2010)
Downloadable copies of all these publications are available at: www.planningportal.gov.uk. Printed paper copies are available from RIBA (see CLG Circular 06/2010).
Please note that the guidance in the publications comes into effect on 1 October 2010, the same date as the amendments to Parts F, J and the energy efficiency requirements made by SI2010/719 and included in SI 2010/2214 come into effect. The use of the guidance is subject to the transitional provisions in the Building Regulations 2010 which are explained in Circulars 03/2010, 06/2010 and 07/2010.
Commencement of work
Some categories in the transitional provisions specify a date by which work must have commenced. In the Department’s opinion the commencement of work would usually be marked by work such as:
•excavation for strip or trench foundations or for pad footings;
•digging out and preparation of ground for raft foundations;
•vibrofloatation (stone columns) piling, boring for piles or pile driving;
•drainage work specific to the building(s) concerned.
The Department considers that the following sorts of work would not be likely to constitute the commencement of work:
•removal of vegetation
Page 3
#Source page 3
•demolition of any previous buildings on the site;
•removal of top soil;
•removal or treatment of contaminated soil;
•excavation of trial holes;
•dynamic compaction;
•general site servicing works (e.g. roadways)
In some cases applications will be in respect of a number of buildings on a site, for example a number of houses. The Department’s opinion is that in such cases it is generally the commencement of work on the first of the buildings within the application which determines whether all the building work can take advantage of the transitional provisions, not each individual building.
Relaxation and dispensation
Local authorities are reminded of the restriction in regulation 11(3) in the Building Regulations 2010 on the power to relax and dispense with requirements, in particular the requirement that buildings must meet target emission rates. The reason for this restriction is to secure implementation of the Energy Performance of Buildings Directive where the requirements in it are absolute ones.
There may be cases where a request for a relaxation or dispensation in these circumstances will arise where an approved inspector is the building control body. Approved inspectors have no powers to relax or dispense. Such relaxation or dispensation requests will have to be made to the local authority concerned either by the approved inspector or the client. Local authorities should deal with such requests in the normal manner and as expeditiously as possible. Local authorities will need evidence to support the request that the operation of the requirements would be unreasonable in the case concerned.
Further guidance on Parts F, J and L and the energy efficiency requirements
The annexes to this letter contain further explanation and guidance for building control bodies on Parts F, J and the energy efficiency requirements of the Regulations.
Enquiries
Any enquiries on this Circular Letter should be addressed as follows:
Part F only: Ken Bromley, Tel: 0303 444 1806
Part J and L: Gerald McInerney, Tel: 0303 444 1775
All e-mail enquiries to enquiries.br@communites.gsi.gov.uk
Page 4
#Source page 4
All letters of enquiry to Sustainable Buildings Division, CLG, 5/E8 Eland House, Bressenden Place, London SW1E 5DU.
Yours Faithfully,

Anthony Burd
Head of Technical Policy
Sustainable Buildings Division
Page 5
#Source page 5
Annex A
New edition of Approved Document F
Amendments to strengthen the requirements of the Building Regulations and Approved Inspectors Regulations for the ventilation of buildings
Introduction
A1The changes to the 2010 Part F requirements and guidance are aimed at ensuring that indoor air quality is not adversely affected by buildings – particularly dwellings – becoming more airtight to meet higher Part L energy efficiency standards. If natural and mechanical ventilation systems are not properly designed, installed, commissioned and operated, then ventilation may be inadequate, leading to excessive levels of moisture and pollutants, and an increased risk of condensation, mould growth and ill-health. In airtight buildings, infiltration through gaps and cracks may not provide sufficient ventilation if the purpose-provided ventilation under-performs or fails. So trickle ventilators, extract fans and ductwork should be correctly sized and installed; and occupants should not tape over draughty trickle ventilators, switch off noisy fans, or allow filters to become blocked.
Changes to Part F requirements and guidance
A2The changes that come into effect on 1 October 2010 are concerned with:
•making provision for more background (trickle) ventilation in intermittent extract and passive stack ventilation systems of dwellings – to compensate for reduced air infiltration through gaps and cracks1
•ensuring that mechanical ventilation systems – which are likely to become more commonplace as we approach zero carbon standards – are properly designed, installed and commissioned
•providing information so that ventilation systems can be properly operated and maintained by occupants.
A3The specific changes to the Building Regulations are:
•a new requirement F1(2) to commission mechanical ventilation systems in dwellings and other buildings
•an addition to regulation 44 (1) adding ventilation systems to the types of building services for which local authorities should be given a notice confirming that commissioning has been carried out
•a new regulation 42 to measure air flow rates for mechanical ventilation systems in new dwellings, and to give the local authority a notice of the results
•a new regulation 39 to provide owners of dwellings and other buildings with information on how to operate and maintain their ventilation system.
These regulations also apply where the building control body is an Approved Inspector. (see regulation 20 of the Building (Approved Inspectors etc.) Regulations)
Page 6
#Source page 6
A4The changes to the approved guidance for dwellings include:
•guidance in Sections 2 and 3 of a new Domestic ventilation compliance guide on installing and inspecting the four ventilation system types (systems 1 to 4) described in detail in Approved Document F (ADF)
•new tables in ADF specifying the total equivalent area of background ventilators for intermittent extract (system 1) and passive stack (system 2) ventilation systems in dwellings
•approved procedures in Sections 2 and 3 of the Domestic ventilation compliance guide for measuring air flow produced by mechanical ventilation systems in new dwellings (including extractor fans and cooker hoods)
•approved procedures in Section 3 of the Domestic ventilation compliance guide for commissioning continuous mechanical extract (system 3) and continuous mechanical supply and extract with heat recovery (system 4) ventilation systems in dwellings
•guidance in Section 4 of the Domestic ventilation compliance guide on the documentation that should be handed over to the end user
•a three-part Inspection checklist and air flow measurement test sheet in Section 5 of the Domestic ventilation compliance guide for recording system details, inspection details, trickle ventilator equivalent areas, air flow measurements, and commissioning details. The persons responsible for the work should sign the sheet, identifying their company and adding if relevant their competent person scheme registration details.
Installation of ventilation systems
A5ADF recommends that ventilation systems should be installed in new and existing dwellings in accordance with the guidance in the Domestic ventilation compliance guide. The guidance in Appendices D and E of the 2006 edition of ADF – on installing passive stack ventilators and fans in dwellings – can now be found in the Domestic ventilation compliance guide along with other guidance.
A6The system installer should complete the installation checklist and inspection sheet in Section 5, recording the equivalent area of any background ventilators so that the total ventilator area can be checked for compliance with Tables 5.2a and 5.2b of ADF. (All trickle ventilators should now be marked with their equivalent area.)
A7Installation guidance for buildings other than dwellings can be found in the references listed in Table 6.3 of ADF.
Air flow rate testing and commissioning of ventilation systems
A8The statutory requirement is for mechanical ventilation systems in dwellings and other buildings to be commissioned (where they can be tested and adjusted) to provide adequate ventilation in accordance with a procedure approved by the Secretary of State. A commissioning notice confirming that commissioning has been carried out must be given to the building control body not later than five days after the work has been completed where a person has submitted a building notice or full plans, or in other cases not later than 30 days after the completion of work.
Page 7
#Source page 7
A9There is also a statutory requirement for air flow rates of mechanical ventilation systems in new dwellings to be measured in accordance with an approved procedure, and for a notice to be given to the building control body not later than five days after the final test is carried out.
A10For dwellings, the approved procedures for measuring air flow rates and for commissioning mechanical ventilation systems are in Sections 2 and 3 of the Domestic ventilation compliance guide. The person responsible for testing and commissioning should complete the air flow measurement test and commissioning sheet in Section 5, an electronic copy of which can be downloaded from www.planningportal.gov.uk. This is the approved manner for recording the results, and should form part of the notice given to the building control body.
A11For commissioning of non-domestic ventilation systems, the approved commissioning procedure is CIBSE Code M.
A12Commissioning of mechanical ventilation systems should ensure that they provide reasonable energy efficiency under Part L as well as adequate ventilation under Part F. It is permissible for the notice of commissioning given to the building control body to cover both.
Provision of information
A13There is a statutory requirement for sufficient information about the ventilation system and its maintenance requirements to be given to owners so that the ventilation system can be operated to provide adequate air flow.
A14For new and existing dwellings, Section 4 of the Domestic ventilation compliance guide lists the documents that it is recommended should be given to the dwelling owner at installation handover.
A15The inspection checklist and air flow measurement test and commissioning sheet in Section 5 should form part of the information pack. An electronic version of the whole of Section 5 can be downloaded from www.planningportal.gov.uk (Part 3 of Section 5, covering air flow measurement and commissioning, is part of the notice given to the building control body - see A10.)
A16For new and existing buildings other than dwellings, a way of showing compliance with the requirement for provision of information is to follow the guidance in Approved Documents L2A and L2B, which refer to the CIBSE TM 31 Building log book toolkit, 2006.
Page 8
#Source page 8
Annex B
New edition of Approved Document J
B1The Part J guidance on ventilation has been revised to ensure that combustion appliances can continue to function safely in more airtight homes. The changes also remove technical disincentives to the wider use of Biomass heating systems. Part J has been amended to introduce a new requirement for carbon monoxide alarms to be fitted where solid fuel appliances are installed. The main changes to the Approved Document are set out below. A number of references, particularly to standards, have been updated throughout the Approved Document. The Approved Document also now draws attention to the requirements of the Clean Air Act 1993.
Section 1
B2There is new guidance for access for visual inspection of concealed flues to ensure that they can be properly inspected, particularly at any joints in the flue, both when an appliance is first commissioned and subsequently serviced.
Section 2
B3Guidance for flue outlet clearances relative to adjacent pitched roofs has been clarified in Diagram 17.
B4To take account of the availability of modern appliances, the guidance on the provision of hearths and wall clearances for solid fuel appliances has been made more flexible.
B5There is a new requirement for the provision of carbon monoxide alarms where new or replacement solid fuel appliances are installed. This affects both new and existing dwellings.
Sections 2, 3 & 4
B6The guidance in Table 1 has been amended to increase the permanent ventilation openings for open flued appliances in airtight houses (with a design air permeability less than or equal to 5 m3/h/m2 @ 50Pa) counteract the decrease in adventitious ventilation relative to older houses. Appendix F of the Approved Document gives advice on assessing the air permeability of older houses in relation to this guidance.
Section 4
B7Section 4 now explicitly includes liquid biofuel and blends on mineral oil and liquid biofuel within the scope of combustion installations designed to burn oil.
Section 5
B8The guidance on identifying where secondary containment for oil tanks is necessary has been expanded to include locations in inner protection zone as shown on the Environment Agency’s groundwater sources map.
Appendix G European chimney designations
B9Appendix G is new and provides and explanation of the European designation system for certain flue and chimney products.
Page 9
#Source page 9
Annex C:
Changes to the energy efficiency requirements
Introduction
C1The effects of the 2010 changes are to strengthen the energy performance standards for new buildings and when building work is carried out to existing buildings and to help builders and building control bodies establish compliance through the introduction of additional calculations, information and testing.
C2The provisions for conservation of fuel and power are set out in:
•requirements relating to thermal elements (regulations 23);
•carbon dioxide (CO 2 ) emission rates (regulation 26);
•consequential improvements (regulation 28);
•energy performance certificates (regulation 29); and
•technical requirements in Part L of Schedule 1.
The above are collectively defined in regulation 2 as the energy efficiency requirements.
C3For new buildings the five criteria for new build compliance introduced in 2006 is retained requiring builders to demonstrate that:
•the CO 2 emission rate target is achieved;
•the design does not fall outside limits of design flexibility;
•the building does not suffer from excessive solar gains;
•the building as constructed delivers the calculated CO 2 performance; and
•information is provided to enable the building to be operated efficiently.
CO 2 Emission Rate Calculations
C4For new buildings a new requirement is introduced (regulation 27(2)), where regulation 26 applies, for CO 2 emission rate calculations to be carried out and given to the Building Control Body along with a list of specifications to which the building is to be constructed not later than a day before the work starts. This is in addition to the CO 2 emission rate calculation required to be submitted not later than 5 days after completion of the work (regulation 27(3)). Although it is possible at design stage that there may be some identical calculations on a development, a CO2 emission rate calculation with supporting information is required to be given to the Building Control Body for each building before commencement of work.
C5Guidance for presenting the evidence that demonstrates compliance with the energy efficiency requirements and highlighting key features that are critical in achieving the annual CO 2 emission rate target can be found at Appendix A to Approved Documents ADL1A and ADL2A. It is anticipated that approved software tools would produce standardised formats for presenting the list of specifications and highlighting key features.
Page 10
#Source page 10
CO2 Emission Rate Targets
C6For new homes the Target Emission Rate is now calculated using SAP2009 and must not exceed the target set by reference to a 2002 standard notional dwelling of the same size and shape as the actual dwelling but with an additional improvement of 25% relative to 2006 standards.
C7The notional dwelling now also includes a party wall heat loss of zero meaning that the targeted improvement of 25% is in addition to treating party walls between connected homes against heat loss. In the actual dwelling secondary heating is only counted as part of the annual CO 2 emission rate of the completed dwelling when actually provided for and credit is allowed wherever low energy lighting is installed. (see paragraphs 5.3 – 5.8 of Approved Document L1A)
C8For new non-domestic buildings, the Target Emission Rate is calculated using 2010 versions of the Simplified Building Energy Model (SBEM) or other approved software tools and must not exceed the target set by reference to a notional building of the same size and shape as the actual building, constructed to a 2010 specification with no improvement factor. Developers have the freedom to vary this concurrent specification provided the Target Emission Rate is achieved or bettered. This concurrent specification takes into account the difficulties/opportunities of improving energy efficiency in different types of building based on relative cost effectiveness of making improvements to typical components. This means some buildings will deliver more than 25% relative to 2006 standards, some less, but overall the improvements are optimised to deliver 25% when applied across the national new non-domestic build mix;
C9SAP 2009 is available at: http://www.bre.co.uk/sap2009/page.jsp?id=1642 and SBEM 2010 (SBEM v4) is available at: http://www.2010ncm.bre.co.uk
Limits of Design Flexibility
C10For all new buildings there has been some strengthening of the limits of design flexibility to ensure minimum standards of energy efficiency are achieved in all cases. Fabric insulation backstops are set out in the Part L Approved Documents and the backstops for fixed building services can be found in the supporting Building Service Compliance Guides.
Limiting the Effects of Solar Gain
C11For new dwellings, Approved Document L1A cites the procedure set out in SAP2009 Appendix P with reasonable provision for limiting heat gains being achieved where the Appendix P procedure indicates that the dwelling will not have a high risk of experiencing high Internal temperatures.
C12For new non-domestic buildings a revised procedure is provided for demonstrating that reasonable provision has been made to limit the effects of solar gain in summer by comparison with a reference glazing system.
Thermal Bridging
C13There is revised guidance on demonstrating reasonable provision for avoiding thermal bridging at construction joints including the option of adopting a quality
Page 11
#Source page 11
assured accredited construction details scheme approach.
C14At the time of publication of this circular letter no accredited construction details schemes have been approved by the Secretary of State. Until such time that accredited construction details schemes have been approved, the calculated value of linear transmittance may be used in SAP without any performance penalty being added where this has been calculated by a suitably experienced and qualified person and the builder has provided information about the way the detail is to be constructed to the Building Control Body.
C15Upon approval of accredited construction details schemes a further circular letter will be issued to reinstate the margins to be applied to the calculation of thermal transmittance as set out at paragraph 5.12(b) to Approved Document L1A and paragraph 5.7(b) to Approved Document L2A.
Air pressure testing
C16The sampling rate for domestic developments has been increased. On each development tests should be carried out on three units of each dwelling type or 50% on all instances of that dwelling type, whichever is less. Also, blocks of flats should be treated as separate developments irrespective of the number of blocks on site.
C17Where a dwelling has been pressure tested this value is used in the completion stage CO 2 emission rate calculation. Where a dwelling has not been pressure tested, the value used in the completion stage CO 2 emission rate calculation is the average test result obtained from other dwellings of the same dwelling type on the development increased by a margin of + 2 m3 /(h.m 2 ) @ 50Pa. For small developments where the builder has opted to avoid pressure testing altogether the value used in the completion stage CO 2 emission rate calculation is 15 m 3 /(h.m 2 ) @ 50Pa.
C18To provide a better test of the airtightness of the building envelope, trickle vents should be temporarily sealed rather than just closed when testing. There are now separate ATTMA (Air Tightness Testing and Measuring Association) Guides for domestic and non-domestic situations. The criteria for non-BINDT (British Institute of Non-Destructive Testing) registered testers has changed and they are now required to demonstrate that their test equipment has been calibrated within the previous 12 months using a UKAS accredited facility.
Commissioning
C19The Part L requirement and guidance on commissioning reflects changes introduced to the Regulations in 2007. Part L1(b)(iii) makes it clear that commissioning means testing and adjusting as necessary to ensure that the fixed building services use no more fuel and power than is reasonable in the circumstances. Regulation 44(2) makes it clear that the requirement on commissioning does not apply where testing and adjustment is not possible or where it would not affect the energy efficiency of the fixed building service.
Page 12
#Source page 12
C20The Approved Document guidance recommends that it would be useful to prepare a commissioning plan, identifying the systems that need to be tested and the tests that will be carried out and provide this with the design stage calculation so that it can be checked that the commissioning is being done as the work proceeds.
C21Where commissioning is necessary the procedures set out in the Domestic Building Services Compliance Guide, the Non-Domestic Building Services Compliance Guide and the Domestic Ventilation Compliance Guide should be followed.
C22The notice of completion of commissioning should be given to the Building Control Body within five days of the completion of the commissioning work. In other cases, for example where work is carried out by a person registered with a competent person scheme (it must be given within 30 days).
Providing Information
C23The person carrying out the building work shall not later than five days after the work has been completed provide to the owner sufficient information so that the building can be operated and maintained efficiently (now set out in Regulation 40 rather than in the Part L1(c) requirement).
Conservatories
C24Building control bodies will wish to note that the exemption from the energy efficiency requirements for conservatories and porches has been clarified. This means that a conservatory will be exempt from the energy efficiency requirements only where: `
•it is at ground level;
•it does not exceed 30 m2 in floor area;
•the walls, windows and doors separating the conservatory or porch from the building to which it is attached have not been removed, or, if removed, have been replaced by a wall window or door which meets the current requirements for energy efficiency for walls, windows and doors; and
•the fixed heating system of the building to which the conservatory or porch is attached has not been extended into the conservatory or porch.
C25Where a conservatory or porch does not meet all of the above conditions it is not exempt and Approved Documents L1B and L2B give guidance on what would be reasonable in meeting the energy efficiency provisions from non-exempt conservatories and porches. Building Control Bodies will want to note that the definition of conservatory in terms of percentage translucent material as set out in previous editions of the Approved Documents no longer applies.
Modular and Portable Buildings
C26As in 2006 and previously, special consideration apply for modular and portable buildings.
Page 13
#Source page 13
C27For the purposes of the Building Regulations, modular and portable buildings with a planned life of more than two years at a given location, should meet the full five criteria set out in the 2010 Approved requirements. However, if more than 70% of the external envelope of the building is to be created from sub-assemblies manufactured prior to 1 October, the 2010 Target Emission Rate should be adjusted as set out in Table 3 of ADL2A.
C28When modular and portable buildings with a planned life of more than two years are to be sited at more than one location (often resulting from distress purchase or hire) the Target Emission Rate/Building Emission Rate should be carried out at the time of construction and can be based on a standard generic configuration. This calculation should then be used as evidence whenever the building is relocated. The supplier should be asked to provide appropriate documentation.
C29Electric heating will be the norm in most modular and portable buildings and this should be compensated for in the Target Emission Rate/Building Emission Rate calculation. There is detailed advice on this in Approved Document L2A.
Shell and Core
C30There is revised guidance on shell and core developments and first fit out work.
C31For a shell and core scheme being offered to market by a developer, the CO2 emission rate calculation before commencement of work needs to demonstrate compliance assuming efficiencies for the fit out works. This ensures that requirements are achievable when the building is subsequently fitted out.
Swimming Pool Basins
C32There is a completely new requirement for swimming pool basins in new or existing buildings. Reasonable provision in most circumstances would be to limit the heat loss by achieving a U-value no less that 0.25 W/m2.K as calculated according to BS EN 13370.
Windows and other controlled fittings
C33The guidance on new or replacement windows in existing dwellings or other buildings has been expanded. The minimum performance standards for windows and doors, as measured by U-values, have been raised. The Window Energy Rating (WER) can be used as an alternative to the U-value. Insulated cavity closers should be fitted where appropriate.
C34Where windows, roof windows, rooflights or glazed doors have to be to a bespoke design (e.g. to match existing retained windows, or in a building in a conservation area), a Window Energy Rating or composite U-value may not be available, and it may be unreasonable to expect the necessary calculations to be done for a one-off unit. Only in such exceptional circumstances (and having agreed it with the relevant Building Control Body and/or Competent Person) may the alternative standard of a centre-pane U-value be accepted.
Renovation of Thermal Elements
C35Thermal elements are walls, roofs or floors that separate a conditioned (heated) space from the external environment. The guidance on the renovation of thermal elements in the Approved Documents has been clarified and expanded in relation
Page 14
#Source page 14
what constitutes ‘renovation’, and the extent of work on individual thermal elements that are captured by the requirement.
C36Schedule 4 of the Regulations has been amended with the effects that where the installation of insulation in a roof or loft space is the only work being carried out there is no requirement to notify building control.
The Approved Documents
C37The layout of the four Approved Documents L has been changed quite extensively from the 2006 versions to improve their general accessibility and to point the reader to places where they can get further help and information.
C38There is amended guidance given for historic and traditional buildings which may have an exemption from the energy efficiency requirements or where special considerations apply.
Building Services Compliance Guides
C39These guides replace the previous Domestic Heating Compliance Guide and Non-Domestic Heating, Cooling and Ventilation Compliance Guides and have been expanded to cover a wider range of fixed building services. They include some guidance that previously appeared in the Approved Documents. They provide guidance for persons installing fixed building services in new and existing buildings to help them comply with building regulations. They cover work on both new systems and replacement systems, identifying the differing standards where these exist.