Avoice Regulations

Scotland Consultations and reviews

Building standards - energy and environmental compliance handbook: consultation proposals

Library captured 10 September 2026

Background

#

Source page 1

Following review and consideration of responses to the July 2024 stage one consultation, regulations amending The Building (Procedure) (Scotland) Regulations 2004 were laid on 12 December 2024. These introduce the requirement for developers to provide an “energy and environmental design statement” with building warrant applications and an “energy and environmental construction statement” with each completion certificate. These statements will describe how the design and construction of the building complies with paragraphs 3.13, 3.14, 3.28, 6.1 to 6.7, 6.10, 7.1 and 7.2 of schedule 5 of the Building (Scotland) Regulations 2004. These are the mandatory standards relevant to the delivery of energy and environmental performance.

Through 2024 and 2025 the Scottish Government has worked with the Scottish Futures Trust and review partners to develop practical guidance to support the completion of the design and construction statements set within the Amendment regulations of 12 December 2024. Application of such guidance is intended to offer a means of demonstrating that an informed and robust approach to compliance has been applied to the standards related to energy and environmental performance.

The draft Energy and Environmental Compliance Handbook is presented for consultation and follows principles already under development for the Compliance Plan Approach but will also be applicable as a stand-alone process.

Consultation questions in relation to this draft handbook can be found in the main consultation document.

Introduction

#

Source page 2

The building standards system in Scotland

The building standards system in Scotland is established by The Building (Scotland) Act 2003 (The 2003 Act). The Act gives powers to Scottish Ministers to make building regulations, procedure regulations, fees regulations and other supporting legislation as necessary, to fulfil the purposes of the Act.

The purpose of the building standards system is to protect the public interest. The system regulates building work on new and existing buildings, to provide buildings that meet reasonable standards which:

Secure the health, safety, welfare and convenience of persons in or about buildings and of others who may be affected by buildings or matters connected with buildings;

Further the conservation of fuel and power; and

Further the achievement of sustainable development.

The thirty-two local authorities in Scotland are appointed by Scottish Ministers as verifiers to administer the building standards system in their geographical areas. Responsibility for compliance with the building regulations lies with the “relevant person” as the party instructing building work and, ultimately, with the building owner.

The building standards system is pre-emptive and is designed to check that proposals meet building regulations. The main principles of the system are that a building warrant must be obtained from a verifier before work commences on site and a completion certificate is accepted by a verifier if, after undertaking reasonable inquiry, they are satisfied the building work meets the building regulations, prior to the building being occupied.

Requirements applicable to building work are set through Building (Scotland) Regulations 2004 as a set of mandatory functional standards. These are statements on what outcomes must be achieved when undertaking building work. These standards are supported by a body of guidance set out in Domestic and Non-domestic Technical Handbooks. This published guidance assists by defining the scope of action expected under each standard by providing one or more examples of how compliance with the standard can be achieved. However, it is quite acceptable to use alternative methods of compliance provided they fully satisfy the regulations.

The Building Standards Division (BSD) is part of the Scottish Government Building Safety and Standards Directorate. Our purpose is to provide and maintain a robust legislative framework to ensure that the building standards system in Scotland protects the public interest. BSD prepares and updates building standards legislation and guidance documents, conducting any necessary research and consults on changes as The 2003 Act requires.

We also work in partnership with Local Authority verifiers and other stakeholders in the delivery and updating of the system and contribute to wider policy objectives of government on issues such as energy efficiency, climate change and building safety.

The Compliance Plan Approach

The Compliance Plan Approach will see the creation of the role of Compliance Plan Manager to oversee compliance with building regulations from concept to completion on behalf of the relevant person and be the verifier’s point of contact to support the verification process. The Compliance Plan Manager’s role would be to support the relevant person and assume responsibility for managing the compliance plan, in which actions of others, which are needed to provide assurance that work is completed in accordance with building regulations and all agreed verification compliance requirements are documented.

The Compliance Plan Manager role will not be introduced until legislative change can be made to provide the role with duties and corresponding offences. The Compliance Plan document has been introduced through recent guidance (early 2026) and sets out the actions and evidence planned to be delivered for an in scope project, record if these were delivered as planned or not, and detail any alternatives to planned measures carried out.

The Building (Procedure) (Scotland) Amendment Regulations 2024

The Building (Procedure) (Scotland) Amendment Regulations 2024 were laid on 12 December 2024. These introduce the requirement for developers to provide an “energy and environmental design statement” with building warrant applications and an “energy and environmental construction statement” with each completion certificate.

These statements will describe how the design and construction of the building complies with paragraphs 3.13, 3.14, 3.28, 6.1 to 6.7, 6.10, 7.1 and 7.2 of schedule 5 of the Building (Scotland) Regulations 2004. These are the mandatory standards relevant to the delivery of energy and environmental performance.

The Energy and Environmental Compliance Handbook

The Energy and Environmental Compliance Handbook explains the procedures set by, and provides practical guidance on meeting, the Building (Procedure) (Scotland) Amendment Regulations 2024.

The regulations are mandatory, but the choice of how to comply lies with the building owner. The Energy and Environmental Compliance Handbook has been issued by Scottish Ministers, through the Building Standards Division, for the purpose of providing practical guidance with respect to the building regulations.

Following The Building (Procedure) (Scotland) Amendment Regulations 2024, all building warrant applications submitted on or after the implementation date will require the submission of an Energy and Environmental Design Statement and an Energy and Environmental Construction Statement. These statements are intended to provide a pathway for the Applicant/Agent/Relevant person to demonstrate to the Verifier that a building meets the minimum energy and environmental standards by providing clear evidence that compliance and assurance processes have been followed.

Who should use this handbook?

Client (Property Developers, Homeowners, etc)

Building Warrant Applicant/Relevant Person

Compliance Plan Manager (when introduced into the system)

Architects / Designers / Agent

Builders and Contractors

Verifiers

Elements of a robust evidence led approach to compliance

#

Source page 3

The application of quality assurance principles should begin at the outset of a project involving a series of component actions that support the delivery of a robust, evidence-led approach to compliance for energy and environmental related elements of the building, including:

Effective engagement and communication between parties

Compliance and assurance require good communication between all project partners in the design and construction of a building, involving:

Client / Building Warrant Applicant / Relevant Person

Design Team / Agent

Builders / Main Contractor

Certifiers of Design

Certifiers of Construction

The Verifier (Building Standards Surveyor/Team)

3rd Party Certifiers

Specialist Consultants / Sub-Contractors / Suppliers /Manufacturers

Risk assessment and mitigation

Risks associated with the design and construction of buildings can be managed and mitigated by:

Identifying clear roles and responsibilities

Drawing on the combined expertise of the team to identify energy and environmental risks

Integration of specialists at the earliest design stage

Explaining the "why" behind design and construction decisions

Adopting a clear procedure for gathering and managing evidence

Controlling wider risks in design decisions, substitutions and changes

Competence and understanding of roles and responsibilities

#

Source page 4

Client (Building Warrant Applicant / Relevant Person)

Employs a competent team to support the preparation of a compliant design, application, build and completion process

Submits collated Design Statement (applicant)

Submits collated Construction Statement (relevant person)

Design Team / Agent

Works collaboratively to produce a compliant energy and environmental design, engaging early with the supply chain and communicating clearly with all parties to mitigate risk

Records and collates evidence to be recorded in the Design Statement

Builder / Main Contractor

Works collaboratively with the design team and supply chain to deliver the energy and environmental design through planning the build, managing any change or substitutions, and communicating clearly with all parties to mitigate construction risks

Records and collates evidence to be recorded in the Construction Statement

Certifiers of Design

Approved Certifiers of Design certify the compliance of a specified aspect of design work against the relevant building regulations.

Certifiers of Construction

At completion, Approved Certifiers of Construction certify that the specified aspects of work comply with all relevant building regulations.

Verifier (Building Standards Surveyor)

Reviews both design statements (through checking of information submitted and building warrant approval) and construction statements (through reasonable inquiry during construction and at the completion stage) and reviews supporting evidence for compliance

Third Party Certifiers

Inspect and certify design and construction work for compliance with Scottish Building Standards during the building warrant process, to support but not replace the statutory responsibilities of Applicants and Verifiers

Specialist Consultants, Subcontractors, Suppliers & Manufacturers

Supply clear, accurate information within their areas of specialism to support compliance of design and construction

Evidence gathering and information management

Throughout both design and construction, comprehensive design information and construction evidence should be gathered and managed to demonstrate compliance, support accountable decision making, and simplify building completion and handover.

Evidenced quality of construction and systems installation, backed up by robust testing, are essential to prevent a performance gap between design intent and delivered buildings.

Typical evidence to demonstrate compliance should include, but not be limited to:

Photographs of key details, junctions, assemblies, equipment, etc

Complete product datasheets and manufacturer’s literature

Materials and products delivery notes

Full testing and commissioning records

Compliance pathway

1. Pre Application

Applicant Agent

Design Team

Develop Design Strategy

Early Engagement

Builder

Specialists

All:

Collaborative Communication

Identify and Manage Risk

Record design decisions AND strategies as the basis of the design and construction evidence packs.

Identify Compliance Route

2. Application

Design Statement

Document Pack

Calculation Pack

Refer to Evidence Schedule, Annex A or B as appropriate to Domestic or Non-Domestic.

3. Construction

Assess and record any changes

Plan

Record

Complete evidence pack throughout

Photos

Delivery Notes

Interim Tests

Check

Build

4. Pre Completion

Construction Statement

Certificates

Testing + Commissioning

Records

Refer to Evidence Schedule, Annex A or B as appropriate to Domestic or Non-Domestic.

5. Completion

Apply Sustainability Label

Provide User Information

Submit Construction Statement

Receive Completion Certificate

Energy and Environmental Requirements

#

Source page 5

Energy and environmental standards

Since the introduction of national building regulations to Scotland in 1964, there have been energy standards, in one form or another. Initially these only applied to the external fabric of certain residential buildings and were minimal in nature. Later, they evolved to take account of commercial and industrial non-domestic buildings and to address the energy efficiency of those building services essential to provide comfort to occupiers of buildings.

Prior to 2000, reviews of energy standards were less frequent, with the outcome of such reviews resulting in modest standards that kept pace with change, but which could be comfortably achieved by all aspects of industry. An impact assessment carried out on subsequent changes over this era would show a cost-benefit for modest improvements which would pay back quickly through reduction in the occupier’s energy bills.

Following the introduction of The 2003 Act and our current system of building standards in May 2005, energy standards within section 6 of the Building Standards Technical Handbooks were reviewed and improved in 2007, 2010, 2015 and most recently in 2023. For new buildings, 2007 saw the introduction of a single means of demonstrating compliance based on calculated carbon dioxide emission targets, using the Standard Assessment Procedure (SAP) for dwellings and the Simplified Building Energy Model (SBEM) (or equivalent) for non-domestic buildings.

Each review introduced further staged improvement to energy standards and related changes on topics such as ventilation. It is assessed that emissions arising from energy use in new buildings constructed to the 2023 standards are, on aggregate, around 32% lower for new homes and 20% lower for new non-domestic buildings, compared to the previous 2015 standards and more than 80% lower than standards in force in 1990, the baseline reporting year for CO2 emissions.

In May 2022, Alex Rowley MSP put forward a draft proposal for a Proposed Building Environmental Standards (Scotland) Bill. This was confirmed in a final proposal of 18 November 2022 for “a Bill to introduce new minimum environmental design standards for all new-build housing to meet a Scottish equivalent to the Passivhaus standard, in order to improve energy efficiency and thermal performance”.

In December 2022, Ministers committed to give effect to the Members’ Bill to deliver ‘a Scottish equivalent to the Passivhaus standard’ with a focus on two outcomes:

Improvements to the setting of energy and environmental (ventilation) performance standards for new buildings, leading to lower energy demand (and reduced running costs) and a healthy indoor environment; and

Improvements to the design and construction process to give greater assurance that compliance, and therefore the performance sought, is delivered in practice.

The Building (Procedure) (Scotland) Amendment Regulations 2024, refers specifically to the following energy and environmental standards:

Section 3 – Environment:

Heating (Standard 3.13)

Ventilation (Standard 3.14)

Overheating Risk (Standard 3.28)

Section 6 – Energy:

Energy Demand (Standard 6.1)

Building Insulation Envelope (Standard 6.2)

Heating System (Standard 6.3)

Insulation of Pipes, Ducts & Vessels (Standard 6.4)

Artificial & Display Lighting (Standard 6.5)

Mechanical Ventilation and Air Conditioning (Standard 6.6)

Commissioning Building Services (Standard 6.7)

Metering (Standard 6.10)

Section 7 – Sustainability:

Statement of Sustainability (Standard 7.1)

Electric Vehicle Charging (Standard 7.2)

Clauses from the Technical Handbooks are referenced in this handbook and schedules A and B. Always refer to the current applicable Standards and Technical Handbooks available from www.gov.scot/collections/building-standards/

Key energy and environmental considerations

Measures fundamental to energy and environmental compliance and assurance include ensuring air tightness, using high-performance windows, doors and insulation products, minimising thermal bridging, providing ventilation that preserves indoor air quality with minimal heat loss, optimising heating, hot-water and power efficiency, and preventing overheating during warm periods.

Design Statement requirements

The Design Statement should include design information to demonstrate that the energy & environmental design presented as part of the building warrant application is achieving the requirements of the relevant mandatory standards.

Schedules A (Domestic) & B (Non-Domestic) of the handbook provide practical guidance on the information to be collated for the relevant mandatory standards respectively.

Each relevant mandatory standard must be addressed in the Design Statement, but supporting information may be collated once and referenced accordingly.

Supporting information should be provided to show that each part of the standard has been considered in the building warrant design by referencing submitted drawings / specification / layout / schedules as appropriate.

Key roles and responsibilities and risk management should also be considered at the design stage, which should be included as part of the Design Statement.

Design information to be gathered and managed

Building and product information, for example:

Design drawings (floor plans, elevations, and sections, etc)

Material specifications and product datasheets (insulation products, window and door performance, etc)

Performance calculations (U-Values, Psi Values, etc)

Energy modelling results

System specifications, for example:

Heating system design and efficiency

Hot water system design and efficiency

Ventilation system design

Construction Statement requirements

The Construction Statement should include evidence during construction as well as ‘as built’ records to demonstrate that the completed building design is achieving the requirements of the relevant energy & environmental mandatory standards.

Schedules A (Domestic) & B (Non-Domestic) of the handbook provide practical guidance on the evidence to be collated for each mandatory standard respectively.

Supporting evidence provided should be cross referenced to the Design Statement as part of the completion submission. Evidence will generally include product and delivery information, as well as photographic evidence of building elements, as appropriate.

Photographs should clearly show installation location and arrangement, related construction details, legible readings, product labels and model numbers, visible measurements (e.g. using a tape measure or ruler) and be taken before covering critical elements. At least 2–5 photos per building element or system depending on complexity, should be provided.

Roles and responsibilities and risk management should also be reconsidered during the planning and build phases of construction, which should be updated and included as part of the Construction Statement.

Construction evidence to be gathered and managed

Delivery notes for materials, products, equipment, etc

Photos of building elements and system installations at key stages

Product labels showing type, specification, etc

Testing results, namely air tightness, as required by mandatory standards, etc

Commissioning certificates

Managing changes during construction

Any changes to the design of the building, or associated specification of elements, during construction, must be:

Submitted for assessment through an amendment to building warrant application

Documented in the Construction Statement

Tested to confirm they still meet standards

Agreed with the Verifier and the Approved Certifier of Design. The amendment to building warrant procedure must also be followed.

Changes typically not requiring an amendment to building warrant are substitutions that maintain or improve performance associated with the relevant Energy or Environmental Mandatory Standard(s).

Changes typically requiring an amendment to building warrant are substitutions that affect energy or environmental performance and associated aspects of the building.

The Verifier will confirm if an amendment to building warrant is required for any changes.

Resources

Specialist support:

Certifiers of Design (Energy)

Energy consultants

Testing specialists

Commissioning specialists

Building Performance specialists

Third Party Certifiers

Verifier / Building Standards Team:

Your local authority building standards department

Building Standards Division:

Scottish Government guidance and technical handbooks available here

Building Standards Hub:

Scottish Building Standards Hub | SBSH

Compliance Plan Approach:

Compliance Plan Approach Workstream

Certification of Design:

Building Standards Certification Handbook

Building Services Compliance Guide:

Domestic Building Services Compliance Guide

Further sources:

CIBSE Guidance Documents (TM23, Guide B, etc.)

Passivhaus Trust (Guidance & Learning Hub, etc.)

Product Certification Schemes (BBA, BM TRADA, etc.)

Schedule A – Domestic

#

Source page 6

Energy and Environmental Compliance

Guidance on gathering information and evidence to support the production of Design and Construction Statements

Section 3 - Environment

Heating (Standard 3.13)

Design Information to support the production of the Energy and Environmental Design Statement

Supporting design information includes, but should not be limited to:

Design drawings

Floor plans showing heating layouts

Specifications

Heating system type

Heat unit specification

Heat emitters specification

Product datasheets

Heating unit manufacturer’s literature

Heating emitters manufacturer’s literature

Performance calculations

Heat loss calculation to a recognised standard

Heating system capacity calculation

Systems design

Heating system performance specification

Heating system capability to be upgraded

Construction Evidence to support the production of the Energy and Environmental Construction Statement

Construction evidence should include, but not be limited to:

Photographs

Heating system as installed

Delivery notes

Heat units

Heat emitters

Product labels

Heat units

Heat emitters

Testing results and reports

Heating system installation records

Commissioning certificates

Heating system commissioning

Handover information

Heating system user handbook / manual

Heating system maintenance requirements

Ventilation (Standard 3.14)

Design Information to support the production of the Energy and Environmental Design Statement

Supporting design information includes, but should not be limited to:

Design drawings

Floor plans showing ventilation layouts (units, fans, ducting, etc)

Layouts showing air transfer paths between rooms

Layouts showing background ventilation

Ventilation schedules

Window/door schedules showing opening area requirements

Layouts showing location of extract fans

Layouts showing location of CO2 monitors

Layouts showing humidistat controls

Layouts showing access for commissioning

Testing and commissioning schedule

Layouts showing access for maintenance

Specifications

Ventilation system type

Ventilation fan(s) specification

Minimum dimension from underside of door leaf to floor required

Background ventilation equivalent area(s)

CO2 monitor

Humidistat controls

Commissioning requirements

Product datasheets

Ventilation unit manufacturer’s literature

Fan manufacturer’s literature

Duct manufacturer’s literature

Transfer grille manufacturer’s literature

Windows/doors and any restrictors

Performance calculations

Ventilation requirement calculation

Background ventilation calculation

Purge ventilation calculation

Extract ventilation rate calculation

Heat recovery calculation

Systems design

Ventilation system performance specification (natural, intermittent mechanical or continuous mechanical)

Ventilation schematic

Commissiong points schematic

Written description of how to operate and maintain the ventilation system

Construction Evidence to support the production of the Energy and Environmental Construction Statement

Construction evidence should include, but not be limited to:

Photographs

Ventilation system as installed

Ventilation units as installed

Extract Fans as installed

Background/trickle vents as installed

Ducting as installed

Transfer grilles as installed

CO2 monitor as installed

Humidistat controls as installed

Demonstrate dimension from underside of door leaf to floor

Demonstrate opening areas of windows/doors/ventilators

Ventilation filters installed

Delivery notes

Ventilation units

Extract Fans

Ducting

Transfer grilles

CO2 monitor

Humidistat controls

Product labels

Ventilation units

Extract Fans

CO2 monitor

Humidistat controls

Testing results and reports

Ventilation system installation records

Commissioning certificates

Ventilation system commissioning reports

Demonstrate accordance with ventilation schedules

Handover information

Ventilation system user handbook / manual

Ventilation system maintenance requirements

Overheating Risk (Standard 3.28)

Design Information to support the production of the Energy and Environmental Design Statement

Supporting design information includes, but should not be limited to:

Design drawings

Drawings and / or schedules illustrating g-values of specific windows/doors (where g-value varies across the project)

Drawing showing opening free area of windows

Elevations and/or detail drawings as required to show shading measures, with sizes noted and orientation

Specifications

Glazing Specification with g-value(s) required

Any shading devices / products

Performance calculations

Glazing calculation(s) showing g-value to 2 decimal places (calculated to EN 410)

Assessment on number of exposed facades and arrangement of openings which provide ventilation to apartments or other habitable spaces

Energy modelling

Overheating Risk – Simple method

Including:

Dimensioned plan drawings

Glazing/floor area ratio calculation

G-valve compensation calculation(s), where required

Overheating Risk – Dynamic thermal analysis modelling including:

TM59 Dynamic thermal modelling report

Reference to drawings recording the building geometry used

Schedule of the fabric U-values, window U-values and g-values, ventilation strategy, permanent shading devices that have been used in the simulation

Specifications or manufacturer's data sheets for the fabric U-values, window U-values and g-values, ventilation strategy,

Details of permanent shading devices

Systems design

Statement on practicality issues considered and assessed for developing the overheating mitigation strategy

Written description of the overheating mitigation systems included in the design (including any provisions made to address site-specific and environmental constraints) and how to operate and maintain them

Description of user control for boost vent & schedules demonstrating boost ventilation rates

Construction Evidence to support the production of the Energy and Environmental Construction Statement

Construction evidence should include, but not be limited to:

Photographs

All elevations as built

All glazing unit label(s) as installed in window / door (showing reference to demonstrate correct unit is installed in the correct component, on correct elevation)

Windows / doors (with any restrictors fitted) demonstrating free area requirement

Any shading devices as installed

Delivery notes

Window / door supplier(s)

Glazing supplier(s)

Any shading devices

Product labels

Window / door supplier(s)

Glazing supplier(s)

Any shading devices

Handover information

User handbook/manual with written description of overheating mitigation systems, including any provisions made to address site-specific and environmental constraints, as well as how to operate and maintain them

Section 6 - Energy

Energy Demand (Standard 6.1)

Design Information to support the production of the Energy and Environmental Design Statement

Supporting design information includes, but should not be limited to:

Energy modelling

Energy Demand Calculation including:

Energy model following UK National Calculation Methodology

Building layout (showing internal floor area), elevations (showing windows, doors and roof profiles) and section drawings (showing floor to floor height and roof profiles)

3D model or calculation showing external wall, floor and roof areas

Site plans showing the orientation and shading objects

Full address and postcode and weather file used

Specification of any low and zero carbon electricity generators

Construction Evidence to support the production of the Energy and Environmental Construction Statement

Construction evidence should include, but not be limited to:

Photographs

Low and zero carbon generating technology (including any inverters for solar PV) as installed

Delivery notes

Low and zero carbon generating technology (including any inverters for solar PV) as installed

Product labels

Low and zero carbon generating technology showing manufacturer and model name (including any inverters for solar PV) as installed

Testing results and reports

As built energy demand calculation

Building Insulation Envelope (Standard 6.2)

Design Information to support the production of the Energy and Environmental Design Statement

Supporting design information includes, but should not be limited to:

Design drawings

Detailed drawings of all external buildups with the material thicknesses and products (material & performance) clearly stated and repeating thermal bridges shown

Drawings that clearly show the locations of all buildups

General arrangement drawings clearly identifying exposed edges and instances of abutting elements

Detailed drawings of cavity separating walls. The material specifications and material thickness should be clearly shown

Window component drawings, elevations and schedules

Plan, section and detail drawings of all key non-repeating thermal bridges and their location with airtight, thermal and windtight lines shown

Markups or labelled model showing the lengths/quantities of all non-repeating thermal bridges

Schedule of all thermal bridges with justification for their assigned psi/chi value (demonstrate that value assigned is conservative stating its source, or provide a calculation in accordance with BS EN ISO 10211: 2017)

Specifications

Insulation products to be used including thickness

State that insulation is to be continuous, with no gaps or voids over 3mm, not be over compressed and be in two layers with offset joints

Insulation, wind & airtight products including tapes and seals to be used at junctions

Other products, including wall ties, masonry support angles and any other thermal bridging elements referencing thermal conductivity of products and any thermal shims or breaks required

All windows, doors and rooflights with manufacturer, model, height, width, frame depth & thickness, glass U-value, glazing g-value, frame U-value and glazing to frame psi value

Products to be used to form and repair the airtight layer stating that membranes, tapes & seals should be applied to firm, solid and clean substrate to aid application and that gaps greater than 6mm in the substrate are not permitted

Products used to seal around service penetrations, window and door openings to the airtight line

Requirement for air tightness testing, the target to be met and the air testing strategy

Any interim air tests with their purpose, process and when they should occur

Product datasheets

Insulation and any other relevant products that includes thermal conductivity and moisture absorptivity where relevant

Products used for sealing any perimeter cavities

All air tightness products used (including any membranes, boards, tapes, etc) stating their air permeability and compatibility with other materials used on the building

Window/Door/Rooflight datasheet with air tightness class stated classification according to BS 12207 (typically class 4)

Performance calculations

U-Value calculations calculated either by using insulation to a thickness derived from manufacturers’ data relating to thermal conductivities (W/mK) and thermal transmittances (U-values: W/m2K) certified by a notified body, or in accordance with BS EN ISO 6946:2017 and for floors adjacent to ground/basements BS EN ISO 13370: 2017

Where the 'space heating demand limit' approach is taken for new dwellings, the reported space heating demand from the SAP model must be below the 'dwelling space heating demand limit'

Calculation to show the overall window/door element U-value using BS EN ISO 10077-1: 2017, BS EN ISO 10077-2: 2017 or (for rooflights) BS EN ISO 12567-2: 2005

Thermal bridge calculation(s) demonstrating minimum surface temperature is within the minimum requirement

Construction Evidence to support the production of the Energy and Environmental Construction Statement

Construction evidence should include, but not be limited to:

Photographs

Each building element (different wall types, roof, soffits, etc.)

Show large overall section of element being represented

Insulation products installed showing type and thickness

Show that the insulation is continuous, with no gaps or voids over 3mm, not over compressed, cut cleanly and in two layers with offset joints

Show that insulation is cut neatly around service penetrations

Each instance of a cavity seal around the perimeter

Show large overall section of element being represented

Show that the cavity is fully filled with a material that limits air movement

Each window/door/rooflight product type installed showing fixings, interface with airtight layer, interface with insulation and overall installation (NB it is not necessary to photograph all windows & doors)

Each of the key junction details as agreed with the verifier to show installation is as designed

Show airtight line / products as installed, fully seated with no gaps or breaks

Show insulation well installed with no voids or gaps over 3mm

Any bridging elements (column, masonry supports etc.) to be photographed with a tape measure to demonstrate it has been installed in line with the design

Typical service penetrations and any additional instances agreed with the verifier

Delivery notes

For each insulation product including manufacturer, product name and lamda value

For each window/door/rooflight product including manufacturer, product name and lamda value

For all airtight layer membranes, tapes & seals

Product labels

For each insulation product including manufacturer, product name and lamda value

For each window/door/rooflight product including manufacturer, product name and lamda value

For all airtight layer membranes, tapes & seals

Testing results and reports

As built general arrangement drawings, including elevations and window/door schedules

As built schedule of thermal bridges with psi values aligned to the as built details

Air tightness test certificate and method statement (It is not necessary to provide any interim tests in the final evidence pack. The builder may choose to hold interim results in their evolving evidence pack as part of their wider risk and quality management process. If so, their status should be clearly identified.)

Heating System (Standard 6.3)

Design Information to support the production of the Energy and Environmental Design Statement

Supporting design information includes, but should not be limited to:

Design drawings

Heating system design drawings

Mechanical schedule

Controls drawings

Specifications

Mechanical specification

Controls specification

Product datasheets

Detailed performance specification or product datasheet of heating system components (giving COP/SCOP (to BS EN 14511-2), if applicable, aligned with system design temperature

Systems design

Design in line with guidance in Compliance Guide in respect to efficiency of heat source, system circulation, system preparation, hot water storage, interlock, zoning, time & temperature controls, flowrate controls, supply temperature, installation, etc

Construction Evidence to support the production of the Energy and Environmental Construction Statement

Construction evidence should include, but not be limited to:

Photographs

Heating system as installed

Heating plant showing model plates

Delivery notes

Heat units

Heat emitters

Product labels

Heat units

Heat emitters

Testing results and reports

As installed heating system modelling calculations

Heating system installation records

Commissioning certificates

Heating system commissioning

Handover information

As installed heating system drawings, schedules and specifications.

Heating system user handbook / manual

Heating system maintenance requirements

Insulation of Pipes, Ducts & Vessels (Standard 6.4)

Design Information to support the production of the Energy and Environmental Design Statement

Supporting design information includes, but should not be limited to:

Specifications

Pipes/ducts - Specification noting insulation products to be used including thickness

Product datasheets

Insulation product datasheet or detailed performance specification

Performance calculations

Vessels - Standing heat loss calculations, backed up with specification of insulation including thickness and thermal conductivity and insulation product datasheet or detailed performance specification

Systems design

Demonstrate that pipes ducts and vessels have been addressed as provided in the section 9 of the Non-domestic Building Services Compliance Guide for Scotland

Construction Evidence to support the production of the Energy and Environmental Construction Statement

Construction evidence should include, but not be limited to:

Photographs

Hot water storage vessel as installed

Insulation thicknesses to pipes and ducts as installed

Show no voids or gaps greater than 3mm between or under insulation

Delivery notes

Hot water storage vessel as installed

Insulation product(s)

Product labels

Hot water storage vessel confirming capacity, standing heat loss and heat exchanger performance

Insulation product(s) including manufacturer and lambda value

Artificial & Display Lighting (Standard 6.5)

Design Information to support the production of the Energy and Environmental Design Statement

Supporting design information includes, but should not be limited to:

Design drawings

Lighting layouts showing number of luminaires and lighting controls

Specifications

Controls description/specification

Product datasheets

Datasheet/ luminaire schedule confirming efficacy (lm/W)

Performance calculations

LENI calculation, if applicable

Systems design

Demonstrate that internal lighting efficiency has been addressed as provided in the section 13 of the Domestic Building Services Compliance Guide for Scotland

Construction Evidence to support the production of the Energy and Environmental Construction Statement

Construction evidence should include, but not be limited to:

Photographs

Each luminaire type as showing extent in typical room

Delivery notes

Each luminaire type as installed

Each controls type as installed

Handover information

Controls user manual(s) / manufacturer’s literature

Mechanical Ventilation and Air Conditioning (Standard 6.6)

Design Information to support the production of the Energy and Environmental Design Statement

Supporting design information includes, but should not be limited to:

Design drawings

Drawings and / or schedules illustrating g-values of specific windows (where g-value varies across the project)

Drawing showing opening free area of windows/doors

Elevations and/or detail drawings as required to show shading measures, with sizes noted

Ventilation schedules/schematics/ layouts showing system requirements and performance

Drawings & specification noting filter type and demonstrating sufficient space for maintenance

Drawings & specification noting controller location & controller specification

Drawings illustrating duct lengths and access for commissioning and maintenance

Details showing any interface of ducts with external envelope and airtight line

Drawings or schematics showing location of any dampers

Specifications

Glazing Specification with g-value(s) required

Description of user control for boost vent & schedules demonstrating boost ventilation rates

Any shading products required

Performance specification of any proposed equipment

Any insulation products to ducting including type, lambda value and thickness - state that insulation is to be continuous with no gaps or voids over 3mm and insulation must not be over compressed

Any airtight dampers

Product datasheets

Ventilation equipment

Insulation to ducting including any tapes, vapour barriers, etc

Performance calculations

Glazing calculation certificate showing g-value to 2 decimal places (calculated to EN 410)

System efficiency calculated at commissioned design flow rate

Systems design

If overheating risk assessment requires cooling, demonstrate that mechanical ventilation and air conditioning efficiency has been addressed as provided in the sections 10 and 11 of the Domestic Building Services Compliance Guide for Scotland

Construction Evidence to support the production of the Energy and Environmental Construction Statement

Construction evidence should include, but not be limited to:

Photographs

Ventilation units as installed showing location(s)

Filters as installed identifying type

Show MVHR / AHU installation with sufficient space for filter removal

Show controller switch location and controller

Show length of cold ducts inside and warm ducts outside the thermal envelope

Demonstrate no voids or gaps greater than 3mm between or under insulation

Show ducts sealed to airtight line of building and duct to MVHR / AHU

Repeat the above for each type of ventilation system used

Delivery notes

Ventilation units as installed

Any filters as installed

Any controls equipment as installed

Insulation products as installed

Ducting as installed

Product labels

Ventilation units as installed

Any filters as installed

Any controls equipment as installed

Insulation products as installed

Ducting as installed

Testing results and reports

As installed system efficiency calculation

Commissioning certificates

Commissioning reports demonstrating ventilation has been commissioned in line with the ventilation schedules

A +5% tolerance is acceptable

Not more than 10% imbalance between total supply and extract

Handover information

As installed drawings, schedules, specifications

Commissioning Building Services (Standard 6.7)

Design Information to support the production of the Energy and Environmental Design Statement

Supporting design information includes, but should not be limited to:

Design drawings

Layouts showing access for commissioning, inspection and maintenance of services

Specifications

Testing & commissioning schedule

Specifications detailing commissioning requirements for MEP systems and any active architectural systems (e.g. powered ventilation openings)

Identify any enhanced load, duration and/or multi-system tests that will be required to demonstrate compliance, in particular for made-to-order equipment or less common systems

Construction Evidence to support the production of the Energy and Environmental Construction Statement

Construction evidence should include, but not be limited to:

Testing results and reports

Report on the outcomes of any commissioning review

Commissioning statements, including commentary and records of the testing and commissioning programme and compliance or variations from the testing and commissioning requirement set out in the design statement

Commissioning certificates

Commissioning certificates for all systems and services

Note – some commissioning evidence will often be included under other sections of the construction statement, and should be clearly referenced as required

Metering (Standard 6.10)

Design Information to support the production of the Energy and Environmental Design Statement

Not applicable to domestic buildings.

Construction Evidence to support the production of the Energy and Environmental Construction Statement

Not applicable to domestic buildings.

Section 7 - Sustainability

Statement of Sustainability (Standard 7.1)

Design Information to support the production of the Energy and Environmental Design Statement

Supporting design information includes, but should not be limited to:

Design drawings

Provide plans, sections, elevations, details, schedules, specification, etc, as appropriate to demonstrate level of sustainability proposed

Specifications

Specify level of sustainability proposed:

Bronze level

Bronze Active level

Silver level

Silver Active level

Gold level

Construction Evidence to support the production of the Energy and Environmental Construction Statement

Construction evidence should include, but not be limited to:

Photographs

Statement of sustainability (sustainability label, or SL) fixed to the building, including the level of sustainability achieved, in a location that is readily accessible, protected from weather and not easily obscured

Other photographs as appropriate for the level of sustainability to demonstrate associated elements as built/as installed

Testing results and reports

Calculations as appropriate for the level of sustainability to demonstrate associated elements as built/as installed

Handover information

Quick start guides/guidance/labels as appropriate for the level of sustainability to demonstrate associated elements as built/as installed

Electric Vehicle Charging (Standard 7.2)

Design Information to support the production of the Energy and Environmental Design Statement

Supporting design information includes, but should not be limited to:

Design drawings

Schedule of equipment

Location of charge points shown on plan drawings

Assignment of any car parking spaces (if applicable)

Duct and chamber layouts and sizes based upon the confirmed schematic arrangement and type of cabling needed to meet the required power supply at outlets for any enabling infrastructure

Specifications

Specification of equipment

Product datasheets

Datasheets for charge points showing nominal rated output and compliance with BS 7671 and IET’s ‘Code of Practice: Electric Vehicle Charging Equipment Installation’

Performance calculations

Electrical demand calculation

Systems design

Written quotation for the cost of electrical supply to development site (if applicable)

Construction Evidence to support the production of the Energy and Environmental Construction Statement

Construction evidence should include, but not be limited to:

Photographs

Each type of equipment as installed

Charge point locations as installed

Electrical meter showing power output from charge points

Assignment of any car parking spaces (if applicable)

Universal socket, indicator/visual display, manufacturer and model

Clear, unobstructed ducts and champers with pulling lines for any enabling infrastructure

Commissioning certificates

Commissioning information for the charge point(s) and any associated control equipment

Handover information

Quick Start guides

Manufacturer’s literature on installed products

As built drawings showing the location of all installed ductwork and equipment, also identifying all enabling infrastructure which will support the addition of charge points in the future

Schedule B – Non-Domestic

#

Source page 7

Energy and Environmental Compliance

Guidance on gathering information and evidence to support the production of Design and Construction Statements

Section 3 - Environment

Heating (Standard 3.13)

Design Information to support the production of the Energy and Environmental Design Statement

Not applicable to non-domestic buildings.

Refer to Schedule A – Domestic for any mixed-use buildings containing dwellings.

Construction Evidence to support the production of the Energy and Environmental Construction Statement

Not applicable to non-domestic buildings.

Refer to Schedule A – Domestic for any mixed-use buildings containing dwellings.

Ventilation (Standard 3.14)

Design Information to support the production of the Energy and Environmental Design Statement

Supporting design information includes, but should not be limited to:

Design drawings

Floor plans showing ventilation layouts (units, fans, ducting, etc)

Layouts showing background ventilation

Layouts showing air transfer paths between rooms

Ventilation schedules

Window/door schedules showing opening area requirements

Layouts showing location of extract fans

Layouts showing location of CO2 monitors

Layouts showing humidistat controls

Layouts showing access for commissioning

Testing and commissioning schedule

Layouts showing access for maintenance

Specifications

Opening areas of ventilators

Ventilation system type

Ventilation fan(s) specification

Louvres, grilles, meshes and other opening obstructions

Minimum dimension from underside of door leaf to floor required

Background ventilation equivalent area(s)

CO2 monitor

Humidistat controls

Commissioning requirements

Product datasheets

Ventilation unit manufacturer’s literature

Fan manufacturer’s literature

Duct manufacturer’s literature

Transfer grille manufacturer’s literature

Windows/doors and any restrictors

Performance calculations

Ventilator opening area requirement(s)

Ventilation requirement calculation

Background ventilation calculation

Purge ventilation calculation

Extract ventilation rate calculation

Heat recovery calculation

Systems design

Ventilation system performance specification (natural, intermittent mechanical or continuous mechanical)

Ventilation schematic

Commissiong points schematic

Written description of how to operate and maintain the ventilation system

Construction Evidence to support the production of the Energy and Environmental Construction Statement

Construction evidence should include, but not be limited to:

Photographs

Ventilation system as installed

Ventilation units as installed

Extract Fans as installed

Background/trickle vents as installed, located in ventilator/window/door

Ducting as installed

Transfer grilles as installed

Louvres, grilles, meshes and other opening obstructions as installed

CO2 monitor as installed

Humidistat controls as installed

Demonstrate dimension from underside of door leaf to floor

Demonstrate opening areas of windows/doors/ventilators

Ventilation filters installed

Access for maintenance

Delivery notes

Ventilation units

Extract Fans

Ducting

Transfer grilles

Louvres, grilles, meshes and other opening obstructions

CO2 monitor

Humidistat controls

Any filters

Product labels

Ventilation units

Extract Fans

Background/trickle Vents

CO2 monitor

Humidistat controls

Testing results and reports

Ventilation system installation records

Commissioning certificates

Ventilation system commissioning reports

Demonstrate accordance with ventilation schedules

Handover information

Ventilation system user handbook / manual

Ventilation system maintenance requirements

Overheating Risk (Standard 3.28)

Design Information to support the production of the Energy and Environmental Design Statement

Supporting design information includes, but should not be limited to:

Design drawings

Drawings and / or schedules illustrating g-values of specific windows/doors (where g-value varies across the project)

Drawing showing opening free area of windows

Elevations and/or detail drawings as required to show shading measures, with sizes noted and orientation

Specifications

Glazing Specification with g-value(s) required

Any shading devices / products

Performance calculations

Glazing calculation(s) showing g-value to 2 decimal places (calculated to EN 410)

Assessment on number of exposed facades and arrangement of openings which provide ventilation to apartments or other habitable spaces

Energy modelling

Overheating Risk – Simple method

Including:

Dimensioned plan drawings

Glazing/floor area ratio calculation

G-valve compensation calculation(s), where required

Overheating Risk – Dynamic thermal analysis modelling including:

TM59 Dynamic thermal modelling report

Reference to drawings recording the building geometry used

Schedule of the fabric U-values, window U-values and g-values, ventilation strategy, permanent shading devices that have been used in the simulation

Specifications or manufacturer's data sheets for the fabric U-values, window U-values and g-values, ventilation strategy,

Details of permanent shading devices

Systems design

Statement on practicality issues considered and assessed for developing the overheating mitigation strategy

Written description of the overheating mitigation systems included in the design (including any provisions made to address site-specific and environmental constraints) and how to operate and maintain them

Description of user control for boost vent & schedules demonstrating boost ventilation rates

Construction Evidence to support the production of the Energy and Environmental Construction Statement

Construction evidence should include, but not be limited to:

Photographs

All elevations

All glazing unit label(s) as installed in window / door (showing reference to demonstrate correct unit is installed in the correct component, on correct elevation)

Windows / doors (with any restrictors fitted) demonstrating free area requirement

Any shading devices as installed

Delivery notes

Window / door supplier(s)

Glazing supplier(s)

Any shading devices

Product labels

Window / door supplier(s)

Glazing supplier(s)

Any shading devices

Handover information

User handbook/manual with written description of overheating mitigation systems, including any provisions made to address site-specific and environmental constraints, as well as how to operate and maintain them

Section 6 - Energy

Energy Demand (Standard 6.1)

Design Information to support the production of the Energy and Environmental Design Statement

Supporting design information includes, but should not be limited to:

Energy modelling

Energy Demand Calculation including:

Energy model following UK National Calculation Methodology

Building layout (showing internal floor area), elevations (showing windows, doors and roof profiles) and section drawings (showing floor to floor height and roof profiles)

3D model or calculation showing external wall, floor and roof areas

Site plans showing the orientation and shading objects

Schedule of shading factors and their justification

Full address and postcode and weather file used

Specification of any low and zero carbon electricity generators

Schedule of management features proposed

Construction Evidence to support the production of the Energy and Environmental Construction Statement

Construction evidence should include, but not be limited to:

Photographs

Low and zero carbon generating technology (including any inverters for solar PV) as installed

Main distribution board including evidence of power factor achieved

Automatic Monitoring and Targeting settings (where relevant)

Delivery notes

Low and zero carbon generating technology (including any inverters for solar PV) as installed

Product labels

Low and zero carbon generating technology showing manufacturer and model name (including any inverters for solar PV) as installed

Testing results and reports

As built energy demand calculation

Building Insulation Envelope (Standard 6.2)

Design Information to support the production of the Energy and Environmental Design Statement

Supporting design information includes, but should not be limited to:

Design drawings

Detailed drawings of all external buildups with the material thicknesses and products (material & performance) clearly stated and repeating thermal bridges shown

Drawings that clearly show the locations of all buildups

Plan and section drawings showing the continuous thermal envelope line

General arrangement drawings clearly identifying exposed edges and instances of abutting elements

Detailed drawings of cavity separating walls. The material specifications and material thickness should be clearly shown

Window component drawings, elevations and schedules

Plan, section and detail drawings of all key non-repeating thermal bridges and their location with airtight, thermal and windtight lines shown

Markups or labelled model showing the lengths/quantities of all non-repeating thermal bridges

Schedule of all thermal bridges with justification for their assigned psi/chi value (demonstrate that value assigned is conservative stating its source, or provide a calculation in accordance with BS EN ISO 10211: 2017)

Specifications

Insulation products to be used including thickness

State that insulation is to be continuous, with no gaps or voids over 3mm, not be over compressed and be in two layers with offset joints

Insulation, wind & airtight products including tapes and seals to be used at junctions

Other products, including wall ties, masonry support angles and any other thermal bridging elements referencing thermal conductivity of products and any thermal shims or breaks required

All windows, doors and rooflights with manufacturer, model, height, width, frame depth & thickness, glass U-value, glazing g-value, frame U-value and glazing to frame psi value

Products to be used to form and repair the airtight layer stating that membranes, tapes & seals should be applied to firm, solid and clean substrate to aid application and that gaps greater than 6mm in the substrate are not permitted

Products used to seal around service penetrations, window and door openings to the airtight line

Requirement for air tightness testing, the target to be met and the air testing strategy

Any interim air tests with their purpose, process and when they should occur

Product datasheets

Insulation and any other relevant products that includes thermal conductivity and moisture absorptivity where relevant

Products used for sealing any perimeter cavities

All air tightness products used (including any membranes, boards, tapes, etc) stating their air permeability and compatibility with other materials used on the building

Window/Door/Rooflight datasheet with air tightness class stated classification according to BS 12207 (typically class 4)

Performance calculations

U-Value calculations calculated either by using insulation to a thickness derived from manufacturers’ data relating to thermal conductivities (W/mK) and thermal transmittances (U-values: W/m2K) certified by a notified body, or in accordance with BS EN ISO 6946:2017 and for floors adjacent to ground/basements BS EN ISO 13370: 2017

Calculation to show the overall window/door element U-value using BS EN ISO 10077-1: 2017, BS EN ISO 10077-2: 2017 or (for rooflights) BS EN ISO 12567-2: 2005

Thermal bridge calculation(s) demonstrating minimum surface temperature is within the minimum requirement

Construction Evidence to support the production of the Energy and Environmental Construction Statement

Construction evidence should include, but not be limited to:

Photographs

For each building element (different wall types, roof, soffits, etc.).

Show large overall section of element being represented

Insulation products installed showing type and thickness

Show that the insulation is continuous, with no gaps or voids over 3mm, not over compressed, cut cleanly and in two layers with offset joints

Show that insulation is cut neatly around service penetrations

For each instance of a cavity seal around the perimeter

Show large overall section of element being represented

Show that the cavity is fully filled with a material that limits air movement

Each window/door/rooflight product type installed showing fixings, interface with airtight layer, interface with insulation and overall installation (NB it is not necessary to photograph all windows & doors)

Each of the key junction details as agreed with the verifier to show installation is as designed

Show airtight line / products as installed, fully seated with no gaps or breaks

Show insulation well installed with no voids or gaps over 3mm

Any bridging elements (column, masonry supports etc.) to be photographed with a tape measure to demonstrate it has been installed in line with the design

Typical service penetrations and any additional instances agreed with the verifier

Delivery notes

For each insulation product including manufacturer, product name and lamda value

For each window/door/rooflight product including manufacturer, product name and lamda value

For all airtight layer membranes, tapes & seals

Product labels

For each insulation product including manufacturer, product name and lamda value

For each window/door/rooflight product including manufacturer, product name and lamda value

For all airtight layer membranes, tapes & seals

Testing results and reports

As built general arrangement drawings, including elevations and window/door schedules

As built schedule of thermal bridges with psi values aligned to the as built details

Air tightness test certificate and method statement (It is not necessary to provide any interim tests in the final evidence pack. The builder may choose to hold interim results in their evolving evidence pack as part of their wider risk and quality management process. If so, their status should be clearly identified.)

Heating System (Standard 6.3)

Design Information to support the production of the Energy and Environmental Design Statement

Supporting design information includes, but should not be limited to:

Design drawings

Heating system design drawings

Hot water system design drawings

Mechanical schedule

Controls drawings

Specifications

Mechanical specification

Controls specification

Product datasheets

Detailed performance specification or product datasheet of heating system components (giving COP/SCOP (to BS EN 14511-2), if applicable, aligned with system design temperature

Performance calculations

Standing heat loss calculations of hot water cylinders and instantaneous water heaters with storage

Systems design

Design in line with guidance in Compliance Guide in respect to efficiency of heat source, system circulation, system preparation, hot water storage, interlock, zoning, time & temperature controls, flowrate controls, supply temperature, installation, etc

Design in line with guidance in Compliance Guide in respect to thermal efficiencies, heat losses and controls.

Construction Evidence to support the production of the Energy and Environmental Construction Statement

Construction evidence should include, but not be limited to:

Photographs

Heating system as installed

Heating plant showing model plates

Equipment, including water heaters, showing model plates

Delivery notes

Heat units

Heat emitter

Product labels

Heat units

Heat emitters

Hot water storage vessel or water heater with storage confirming capacity, standing heat loss and heat exchanger performance

Testing results and reports

As installed heating system modelling calculations

Heating system installation records

Datasheet giving COP/SCOP, if applicable, for installed plant

Commissioning certificates

Heating system commissioning

Handover information

As installed heating system drawings, schedules and specifications.

Heating system user handbook / manual

Heating system maintenance requirements

Insulation of Pipes, Ducts & Vessels (Standard 6.4)

Design Information to support the production of the Energy and Environmental Design Statement

Supporting design information includes, but should not be limited to:

Specifications

Pipes/ducts - Specification noting insulation products to be used including thickness

Product datasheets

Insulation product datasheet or detailed performance specification

Performance calculations

Vessels - Standing heat loss calculations, backed up with specification of insulation including thickness and thermal conductivity and insulation product datasheet or detailed performance specification

Systems design

Demonstrate that pipes ducts and vessels have been addressed as provided in the section 9 of the Non-domestic Building Services Compliance Guide for Scotland

Construction Evidence to support the production of the Energy and Environmental Construction Statement

Construction evidence should include, but not be limited to:

Photographs

Hot water storage vessel as installed confirming capacity, standing heat loss and heat exchanger performance

Insulation thicknesses to pipes and ducts as installed

Show no voids or gaps greater than 3mm between or under insulation

Delivery notes

Hot water storage vessel

Insulation product(s) showing label of product, manufacturer and lambda value

Product labels

Hot water storage vessel confirming capacity, standing heat loss and heat exchanger performance

Insulation product(s) including manufacturer and lambda value

Artificial & Display Lighting (Standard 6.5)

Design Information to support the production of the Energy and Environmental Design Statement

Supporting design information includes, but should not be limited to:

Design drawings

Lighting layouts showing number of luminaires and lighting controls

Specifications

Controls description/specification

Product datasheets

Datasheet/ luminaire schedule confirming efficacy (lm/W)

Performance calculations

LENI calculation, if applicable

Systems design

Demonstrate that internal lighting efficiency has been addressed as provided in the section 13 of the Domestic Building Services Compliance Guide for Scotland

Construction Evidence to support the production of the Energy and Environmental Construction Statement

Construction evidence should include, but not be limited to:

Photographs

Each luminaire type as installed showing extent in typical room

Delivery notes

Each luminaire type as installed

Each controls type as installed

Handover information

Controls user manual(s) / manufacturer’s literature

Mechanical Ventilation and Air Conditioning (Standard 6.6)

Design Information to support the production of the Energy and Environmental Design Statement

Supporting design information includes, but should not be limited to:

Design drawings

Drawings and / or schedules illustrating g-values of specific windows (where g-value varies across the project)

Drawing showing opening free area of windows/doors

Elevations and/or detail drawings as required to show shading measures, with sizes noted

Ventilation schedules/schematics/ layouts showing system requirements and performance

Drawings & specification noting filter type and demonstrating sufficient space for maintenance

Drawings & specification noting controller location & controller specification

Drawings illustrating duct lengths and access for commissioning and maintenance

Details showing any interface of ducts with external envelope and airtight line

Drawings or schematics showing location of any dampers

Specifications

Ventilation equipment

Glazing Specification with g-value(s) required

Description of user control for boost vent & schedules demonstrating boost ventilation rates

Any passive shading strategy/shading products required

Performance specification of any proposed equipment

Any insulation products to ducting including type, lambda value and thickness - state that insulation is to be continuous with no gaps or voids over 3mm and insulation must not be over compressed

Any airtight dampers

Product datasheets

Ventilation equipment

Insulation to ducting including any tapes, vapour barriers, etc

Performance calculations

TM52 (or TM59 for sleeping accommodation) study and report, or

Overheating report from a Dynamic Simulation Model Glazing calculation certificate showing g-value to 2 decimal places (calculated to EN 410), or

Simple Method

System efficiency calculated at commissioned design flow rate

Systems design

If overheating risk assessment requires cooling, demonstrate that mechanical ventilation and air conditioning efficiency has been addressed as provided in the sections 10 and 11 of the Domestic Building Services Compliance Guide for Scotland

Construction Evidence to support the production of the Energy and Environmental Construction Statement

Construction evidence should include, but not be limited to:

Photographs

Ventilation units as installed showing location(s)

Filters as installed identifying type

Showing MVAC, MVHR / AHU installation with sufficient space for filter removal

Showing controller switch location and controller

Showing length of cold ducts inside and warm ducts outside the thermal envelope

Demonstrate no voids or gaps greater than 3mm between or under insulation

Show ducts sealed to airtight line of building and duct to MVAC / MVHR / AHU

Repeat the above for each type of ventilation system used

Any passive shading installed showing extent of shading on each elevation and depth of each device

Delivery notes

Ventilation units as installed

Any filters as installed

Any controls equipment as installed

Insulation products as installed

Ducting as installed

Product labels

Ventilation units as installed

Any filters as installed

Any controls equipment as installed

Insulation products as installed

Ducting as installed

Testing results and reports

As installed system efficiency calculation

Commissioning certificates

Commissioning reports demonstrating ventilation has been commissioned in line with the ventilation schedules

A +5% tolerance is acceptable

Not more than 10% imbalance between total supply and extract

Handover information

As installed drawings, schedules, specifications

Commissioning Building Services (Standard 6.7)

Design Information to support the production of the Energy and Environmental Design Statement

Supporting design information includes, but should not be limited to:

Design drawings

Layouts showing access for commissioning, inspection and maintenance of services

Specifications

Testing & commissioning schedule

Specifications detailing commissioning requirements for MEP systems and any active architectural systems (e.g. powered ventilation openings)

Identify any enhanced load, duration and/or multi-system tests that will be required to demonstrate compliance, in particular for made-to-order equipment or less common systems

Ductwork leakage testing, if applicable, set out in Testing & Commissioning Schedule, and MEP specification as above

Construction Evidence to support the production of the Energy and Environmental Construction Statement

Construction evidence should include, but not be limited to:

Testing results and reports

Report on the outcomes of any commissioning review

Commissioning statements, including commentary and records of the testing and commissioning programme and compliance or variations from the testing and commissioning requirement set out in the design statement

Commissioning certificates

Commissioning certificates for all systems and services

Note – some commissioning evidence will often be included under other sections of the construction statement, and should be clearly referenced as required

Metering (Standard 6.10)

Design Information to support the production of the Energy and Environmental Design Statement

Supporting design information includes, but should not be limited to:

Design drawings

Schematics showing metering locations for new or modified energy systems, as applicable

Metering & Verification Schedule, showing service, purpose and means of monitoring for each meter

Construction Evidence to support the production of the Energy and Environmental Construction Statement

Construction evidence should include, but not be limited to:

Photographs

Each meter installation

Commissioning certificates

Commissioning Statements

As built record of metering including use reference and labelling evidence

Section 7 - Sustainability

Statement of Sustainability (Standard 7.1)

Design Information to support the production of the Energy and Environmental Design Statement

Supporting design information includes, but should not be limited to:

Design drawings

Provide plans, sections, elevations, details, schedules, specification, etc, as appropriate to demonstrate level of sustainability proposed

Specifications

Specify level of sustainability proposed:

Bronze level

Bronze Active level

Silver level

Silver Active level

Gold level

Construction Evidence to support the production of the Energy and Environmental Construction Statement

Construction evidence should include, but not be limited to:

Photographs

Statement of sustainability (sustainability label, or SL) fixed to the building, including the level of sustainability achieved, in a location that is readily accessible, protected from weather and not easily obscured

Other photographs as appropriate for the level of sustainability to demonstrate associated elements as built/as installed

Testing results and reports

Calculations as appropriate for the level of sustainability to demonstrate associated elements as built/as installed

Handover information

Quick start guides/guidance/labels as appropriate for the level of sustainability to demonstrate associated elements as built/as installed

Electric Vehicle Charging (Standard 7.2)

Design Information to support the production of the Energy and Environmental Design Statement

Supporting design information includes, but should not be limited to:

Design drawings

Schedule of equipment

Location of charge points shown on plan drawings

Assignment of any car parking spaces (if applicable)

Duct and chamber layouts and sizes based upon the confirmed schematic arrangement and type of cabling needed to meet the required power supply at outlets for any enabling infrastructure

Specifications

Specification of equipment

Product datasheets

Datasheets for charge points showing nominal rated output and compliance with BS 7671 and IET’s ‘Code of Practice: Electric Vehicle Charging Equipment Installation’

Performance calculations

Electrical demand calculation

Systems design

Written quotation for the cost of electrical supply to development site (if applicable)

Construction Evidence to support the production of the Energy and Environmental Construction Statement

Construction evidence should include, but not be limited to:

Photographs

Each type of equipment as installed

Charge point locations as installed

Electrical meter showing power output from charge points

Assignment of any car parking spaces (if applicable)

Universal socket, indicator/visual display, manufacturer and model

Clear, unobstructed ducts and champers with pulling lines for any enabling infrastructure

Commissioning certificates

Commissioning information for the charge point(s) and any associated control equipment

Handover information

Quick Start guides

Manufacturer’s literature on installed products

As built drawings showing the location of all installed ductwork and equipment, also identifying all enabling infrastructure which will support the addition of charge points in the future

Statements Template

#

Source page 8

Template to support the production of Design and Construction Statements

Building Standards Energy and Environmental Compliance

Design Statement*

Construction Statement*

(* delete as appropriate for submission stage)

Project Name:

Applicant:

Application Reference No:

[Template: This document is provided to support production of the Energy and Environmental Design Statement as part of the building warrant application followed by the submission of the Energy and Environmental Design Statement at the completion stage]

Section 3 - Environment

Heating (Standard 3.13)

Design InformationConstruction Evidence
[Insert as appropriate to support building warrant application] (Not applicable to non-domestic projects)[Insert as appropriate to support building warrant application] (Not applicable to non-domestic projects)
(add rows for each distinct element/product/system/equipment)(add rows for each distinct element/product/system/equipment)

Ventilation (Standard 3.14)

Design InformationConstruction Evidence
[Insert as appropriate to support building warrant application][Insert as appropriate to support completion submission]

Overheating Risk (Standard 3.28)

Design InformationConstruction Evidence
[Insert as appropriate to support building warrant application][Insert as appropriate to support completion submission]

Roles & Responsibilities

Element / RoleOwnerContributor
[add as appropriate] (e.g. heating system design) (e.g. Applicant / Relevant Person / Designer / Builder / Main Contractor / 3rd Party Certifier / Specialist Consultant / Sub-Contractor /Supplier)xN/A
[add rows as appropriate]xx

Risk Management

RiskOwnerMitigation
[add as appropriate][add as appropriate][add as appropriate]
[add rows as appropriate][add as appropriate][add as appropriate]

Section 6 - Energy

Energy Demand (Standard 6.1)

Design InformationConstruction Evidence
[Insert as appropriate to support building warrant application][Insert as appropriate to support completion submission]
(add rows for each distinct element/product/system/equipment)(add rows for each distinct element/product/system/equipment)

Building Insulation Envelope (Standard 6.2)

Design InformationConstruction Evidence
[Insert as appropriate to support building warrant application][Insert as appropriate to support completion submission]

Heating System (Standard 6.3)

Design InformationConstruction Evidence
[Insert as appropriate to support building warrant application][Insert as appropriate to support completion submission]

Insulation of Pipes, Ducts & Vessels (Standard 6.4)

Design InformationConstruction Evidence
[Insert as appropriate to support building warrant application][Insert as appropriate to support completion submission]

Artificial & Display Lighting (Standard 6.5)

Design InformationConstruction Evidence
[Insert as appropriate to support building warrant application][Insert as appropriate to support completion submission]

Mechanical Ventilation and Air Conditioning (Standard 6.6)

Design InformationConstruction Evidence
[Insert as appropriate to support building warrant application][Insert as appropriate to support completion submission]

Commissioning Building Services (Standard 6.7)

Design InformationConstruction Evidence
[Insert as appropriate to support building warrant application][Insert as appropriate to support completion submission]

Metering (Standard 6.10)

Design InformationConstruction Evidence
[Insert as appropriate to support building warrant application][Insert as appropriate to support completion submission]

Roles & Responsibilities

Element / RoleOwnerContributor
[add as appropriate] (e.g. energy performance calculations) (e.g. Applicant / Relevant Person / Designer / Builder / Main Contractor / 3rd Party Certifier / Specialist Consultant / Sub-Contractor /Supplier)xN/A
[add rows as appropriate]xx

Risk Management

RiskOwnerMitigation
[add as appropriate][add as appropriate][add as appropriate]
[add rows as appropriate][add as appropriate][add as appropriate]

Section 7 - Sustainability

Statement of Sustainability (Standard 7.1)

Design InformationConstruction Evidence
[Insert as appropriate to support building warrant application][Insert as appropriate to support completion submission]
(add rows for each distinct element/product/system/equipment)(add rows for each distinct element/product/system/equipment)

Electric Vehicle Charging (Standard 7.2)

Design InformationConstruction Evidence
[Insert as appropriate to support building warrant application][Insert as appropriate to support completion submission]

Roles & Responsibilities

Element / RoleOwnerContributor
[add as appropriate] (e.g. Sustainability Label(s)) (e.g. Applicant / Relevant Person / Designer / Builder / Main Contractor / 3rd Party Certifier / Specialist Consultant / Sub-Contractor /Supplier)xN/A
[add rows as appropriate]xx

Risk Management

RiskOwnerMitigation
[add as appropriate][add as appropriate][add as appropriate]
[add rows as appropriate][add as appropriate][add as appropriate]

Declaration:

Design Statement

I/We declare that an evidence‑led approach to compliance has been followed in the development of the design proposals through collaboration amongst the design team, identifying key roles and responsibilities, assessing any project risks and putting in place mitigation strategies, and robust processes for information management and evidence gathering.

Applicant / Agent (delete as appropriate)

Print Name:

Date:

Signature:

Construction Statement

I/We declare that an evidence‑led approach to compliance has been followed in the construction of the building through collaboration amongst the design team, contractor and supply chain identifying key roles and responsibilities, assessing any building performance risks and putting in place mitigation strategies, and robust processes for information management and evidence gathering, including change control as appropriate.

Relevant Person

Print Name:

Date:

Signature:

Your next step

Meet your mini assistant.

Sign up to ask questions about Building Regulations and explore the guidance with Avoice.

Sign up

Already have an account? Log in

Already an Avoice customer? Log in