How to Read a Fee Burn Report
Turn hours, fees and progress into a clear signal for each stage, and know what to do about it.
A fee burn report compares what each stage has cost with what it has earned. This guide explains every column, works through an illustrative three-stage project and sets out what each pattern usually means and the action it calls for.
A fee burn report sets the value of hours spent on each stage against the fee that progress has earned.
What a fee burn report shows
A fee burn report compares, for each stage of a project, how much of the fee has been spent in hours with how much has been earned by progress. The gap between the two is the early warning of an overrun or the sign of a stage running well.
Most practices can see hours used against a budget. That number alone is misleading. A stage that has used 60% of its hours is fine if the work is 65% done and in trouble if it is 40% done. A fee burn report adds the missing piece, percentage complete, and turns it into money and hours the practice can act on.
The method is a simple form of what project managers call earned value. It needs three inputs per stage: a fee with an hours budget, hours recorded on approved timesheets, and an honest estimate of percentage complete from the project lead.
Spent
Hours on approved timesheets, as a share of the stage budget.
Earned
The project lead's estimate of progress, applied to the fee.
Spending 60% of the budget to complete 50% of the work means the stage is heading for an overrun of about a fifth. Figures are illustrative.
Every column, explained
Seven figures make up a useful fee burn report. Each is simple; reading them together is what gives the signal.
- Fee
- The agreed fee for the stage, excluding additional services, which should have their own lines.
- Budget hours
- The fee divided by the blended hourly rate for the expected team. £30,000 at £75 per hour is 400 hours.
- Hours to date
- Hours recorded against the stage on approved timesheets.
- Percentage complete
- The project lead's estimate of how much of the stage's work is done, judged on deliverables, not on hours.
- Earned fee
- Fee multiplied by percentage complete. In hours, this is the earned hours: budget hours multiplied by percentage complete.
- Variance
- Earned hours minus hours to date. Negative means the stage has used more hours than its progress justifies.
- Estimate to complete
- The hours still needed to finish the stage, and from it the forecast total at completion.
Percentage complete is the column that needs most care. If it is taken from hours used, the report will always say the stage is on track. Ask the project lead to judge it from the drawings, specification and coordination work still outstanding, ideally against a short list of stage deliverables.
A worked three-stage example
The illustrative project below has three stages at a blended rate of £75 per hour. The totals look almost on budget; the stages tell three different stories.
Stage 2, Concept Design: closed
Fee £24,000, budget 320 hours. Hours to date 352, 100% complete. Earned hours 320, so the variance is minus 32 hours, worth £2,400 at the blended rate. The stage is finished and the overrun is fixed.
Stage 3, Spatial Coordination: running behind
Fee £30,000, budget 400 hours. Hours to date 240, 50% complete. Earned fee £15,000 and earned hours 200, so the variance is minus 40 hours, worth £3,000. If the second half goes the way the first half did, the stage will take 240 divided by 0.5, which is 480 hours in total. The estimate to complete is 240 hours and the forecast overrun is 80 hours, worth £6,000.
Stage 4, Technical Design: running ahead
Fee £45,000, budget 600 hours. Hours to date 150, 30% complete. Earned fee £13,500 and earned hours 180, so the variance is plus 30 hours, worth £2,250. At the current pace the stage would take 150 divided by 0.3, which is 500 hours, finishing 100 hours under budget.
The project total
Total fee £99,000 and budget 1,320 hours. Hours to date 742 and earned hours 700, a variance of minus 42 hours, worth £3,150. The forecast total at completion is 352 plus 480 plus 500, which is 1,332 hours, only 12 hours over budget. A project-level report would show nothing to worry about. The stage view shows a closed overrun, a live one that needs action now and an early saving in Stage 4 that may not last.
A project total that looks fine is often two stage problems cancelling each other out.
Three ways to estimate to complete
Estimate to complete is the column directors act on, so it should be the most considered. There are three common methods, and comparing them is often more useful than choosing one.
For Stage 3 in the example
- Remaining budget: Assume the rest goes to plan. 400 budget hours less 200 earned hours leaves 200 hours to complete, 440 in total.
- Current pace: Assume the rest goes the way it has so far. Hours to date divided by percentage complete gives 480 in total, so 240 to complete.
- Bottom-up: Ask the project lead to list the remaining tasks and estimate each. This is the most reliable, and the other two methods are a check on it.
When the bottom-up figure is close to the remaining budget but well below the current-pace figure, ask what will make the second half of the stage faster than the first. Sometimes there is a good answer, such as a design freeze that has now happened. Often there is not.
Some practices also track a cost performance index: earned fee divided by the value of hours spent. In the example, Stage 3 is £15,000 divided by £18,000, about 0.83, and Stage 4 is £13,500 divided by £11,250, which is 1.2. Below 1 means each hour is earning less fee than planned.
What each pattern suggests
Most fee burn reports show one of four patterns for each stage. Each points to a different conversation, and the earlier it happens the more options the practice has.
- 01
On track
Hours used within a few points of progress.
- Likely cause
- Budget and team were right
- Action
- Keep reviewing weekly; record actuals for future proposals
- 02
Running ahead
Progress ahead of hours used.
- Likely cause
- Efficient team, or percentage complete is optimistic
- Action
- Test the estimate against deliverables before banking the saving
- 03
Slow progress
Few hours and little progress against the programme.
- Likely cause
- Waiting on client or consultants, or team pulled elsewhere
- Action
- Check the programme and resourcing; record client delays
- 04
Burning ahead
Hours used well ahead of progress.
- Likely cause
- Scope creep, rework, design changes or a too-senior team
- Action
- Price changes as additional services, rebalance the team or agree a revised fee
Burning ahead is the pattern to act on fastest, because the options narrow every week the stage stays open.
- Review weekly.A report seen once a month is a record, not a control.
- Separate additional services.Out-of-scope work on its own line keeps the stage honest and billable. See additional services and variations.
- Agree a threshold.For example, any stage where hours used are 10 points ahead of progress is discussed at the next project review.
- Feed it forward.Final hours per stage are the best evidence for the next fee proposal.
Questions practices ask
Short answers to the fee burn questions UK practices ask most often.
What is fee burn in architecture?
Fee burn is the rate at which a project or stage uses up its fee, measured by the value of hours recorded against it. It is meaningful only when compared with progress, so most practices report hours used against percentage complete for each RIBA stage.
How do you calculate earned value for an architecture project?
Multiply each stage's fee by its percentage complete. A £30,000 stage that is 50% complete has earned £15,000. Compare that with the value of hours spent to see whether the stage is ahead of or behind budget.
How do you calculate estimate to complete?
Three common ways: remaining budget hours, current pace (hours to date divided by percentage complete, less hours to date) or a bottom-up estimate of remaining tasks. The bottom-up estimate is usually the most reliable, with the other two as a check.
How often should architects review fee burn?
Weekly for live stages, as part of a short project review. Monthly reviews tend to find overruns after the options to fix them have gone.
Who should estimate percentage complete?
The project lead, judging the deliverables still outstanding rather than the hours used. A director should challenge the estimate when it moves in step with hours every week.
Where Avoice fits
Avoice builds the fee burn picture from timesheets and stage fees that are already in the same project, so the report is current whenever someone looks.
In Avoice, each project carries its RIBA stages, fees and hours budgets. Timesheets, with hours suggested from project activity and approved weekly, roll up against each stage. Financials and cash flow show fees invoiced, WIP, margin and project profitability, synced with Xero or QuickBooks. For setting up the stage codes behind the report, see how to track time against RIBA stages.
To see fee burn for one of your own projects, book a demo.