How to Calculate Architects' Fees in the UK
Build the fee from the hours the work needs, check it against the market, and write it into the appointment properly.
There is no fee scale for UK architects, so every fee is a judgement. This guide shows how to build a fee bottom-up by RIBA stage, check it as a percentage of construction cost, and protect it in the appointment.
Price the hours the work needs first, then compare the total with similar projects as a percentage of construction cost.
There is no fee scale, so the fee is yours to build
UK architects do not work to a mandatory fee scale. Every practice sets its own fees, which means every fee is a judgement about the work, the risk and the client. The practices that protect their margin are the ones that build that judgement on their own data.
Many fees are still set by feel: a percentage that worked last time, adjusted for how much the practice wants the job. That approach fails quietly. A fee that looks reasonable as a percentage can hide a Stage 4 that needs twice the hours the practice has allowed, and the gap only appears when the team is already doing the work.
A sound fee is built from the work itself, then checked against the market. The rest of this guide sets out how.
Four ways to charge
Most appointments use one of four bases, or combine them across stages. Each moves risk between the practice and the client in a different way.
- 01
Lump sum
A fixed fee per stage or for the whole appointment.
- Good for
- Clear, well-defined scope
- Risk
- Overruns are the practice's problem unless scope change is priced
- 02
Percentage
A percentage of construction cost.
- Good for
- Scope that scales with the build
- Risk
- Fee falls if the budget is cut but the work does not
- 03
Hybrid
Lump sum early stages, percentage or time later.
- Good for
- Projects with an uncertain brief
- Risk
- Needs careful definition of where each basis applies
- 04
Time charge
Hourly or daily rates, sometimes capped.
- Good for
- Feasibility, advice, undefined or open-ended work
- Risk
- Clients resist uncapped fees; caps return risk to the practice
Whichever basis you quote, build the number from hours first. The basis is how you present it, not how you calculate it.
Build the fee bottom-up
Start with the work. Estimate the hours each stage will need, by role, then price those hours. This is the number you need to make money, whatever basis the client sees.
Work through it in this order
- Scope: Confirm which RIBA stages and which services you are appointed for, and what is excluded.
- Hours by stage: Estimate hours per stage by role, using actual hours from similar past projects where you have them.
- Rates: Apply charge-out rates per role, or a blended rate per stage based on the expected team mix.
- Expenses: Add travel, printing, surveys and other disbursements, or state how they will be charged.
- Coordination: Allow time to manage consultants, client meetings and statutory submissions, which are easy to under-count.
- Risk: Add an allowance for brief uncertainty, a difficult site or a client who is new to building.
- Check: Convert the total to a percentage of construction cost and compare it with similar jobs.
A worked example
An illustrative one-off new-build house with a construction cost of £600,000, appointed for Stages 1 to 6. The practice estimates hours from two similar past projects and uses a blended rate of £85 per hour.
- Stage 1
- 30 hours · £2,550 · about 5% of the fee
- Stage 2
- 80 hours · £6,800 · about 13%
- Stage 3
- 120 hours · £10,200 · about 20%
- Stage 4
- 220 hours · £18,700 · about 36%
- Stage 5
- 140 hours · £11,900 · about 23%
- Stage 6
- 20 hours · £1,700 · about 3%
- Total
- 610 hours · £51,850 before expenses and risk allowance · about 8.6% of construction cost
The stage split that falls out of the hours is more useful than a split copied from a template, because it reflects how this practice actually works. Here, Technical Design carries more than a third of the fee, which is common when the practice writes the specification and coordinates detailed design in-house.
- 1
About 5%
Brief, surveys and appointment. 30 hours.
- 2
About 13%
Concept options and client reviews. 80 hours.
- 3
About 20%
Coordination and planning. 120 hours.
- 4
About 36%
Drawings, specification, tender. 220 hours.
- 5
About 23%
Site visits, RFIs, instructions. 140 hours.
- 6
About 3%
Handover and close-out. 20 hours.
Shares of the illustrative £51,850 fee, derived from estimated hours per stage rather than copied from a template.
Check it top-down, then adjust the scope, not the rate
Once you have a bottom-up number, compare it with what the market and the client will bear. If the two do not meet, change what you are offering rather than quietly cutting the hours you know the work needs.
Compare the fee as a percentage of construction cost with your own similar projects. Smaller, more complex and heritage projects tend to sit higher as a percentage than large, repetitive ones, because the design effort does not shrink in proportion to the build.
If the client's budget is below your number, the honest options are to reduce scope (fewer stages, partial services, fewer site visits), change the basis (a time charge for an uncertain early stage) or walk away. Cutting the rate while keeping the scope just moves the overrun into Stage 4.
A fee is a budget for hours. If you would not accept the hours, do not accept the fee.
Put it in the appointment properly
A good fee can still be lost in a vague appointment. The proposal and the appointment should make the scope, the basis and what happens when things change completely clear.
- Services listed by RIBA stage, with clear exclusions.
- Fee basis and amount per stage, and how a percentage fee is recalculated if the construction cost changes.
- Hourly rates by role for additional services and variations.
- Caps on items such as site visits or design options, and the rate beyond them.
- A payment schedule tied to stages or monthly instalments, with payment terms.
- Whether figures include or exclude VAT, which VAT-registered practices charge at the standard rate.
- How expenses are charged.
Then carry the stage fees straight into the project budget so the team can track against them. See how to track time against RIBA stages.
Questions practices ask
Short answers to the fee questions UK architects and their clients ask most.
Is there a standard fee scale for architects in the UK?
No. There is no mandatory fee scale. Each practice sets its own fees, usually as a percentage of construction cost, a lump sum, a time charge or a combination, and should check them against the resources the job will need.
How do architects calculate their fees?
The most reliable method is bottom-up: estimate the hours each stage will need by role, multiply by charge-out rates, add expenses, consultant coordination and a risk allowance, then check the total as a percentage of construction cost against similar past projects.
How much does an architect cost in the UK?
It depends on size, complexity, scope and how many stages the architect is appointed for. Full-service fees for one-off residential work are often quoted somewhere between the mid single digits and the mid teens as a percentage of construction cost, with smaller and more complex projects at the higher end. Partial services cost less.
How should fees be split across RIBA stages?
Base the split on estimated hours for each stage rather than a fixed template. In practices that produce detailed technical information in-house, Stage 4 usually carries the largest share.
Do architects charge VAT?
VAT-registered practices charge VAT on their fees at the standard rate. Proposals should state whether figures include or exclude VAT.
Where Avoice fits
In Avoice, the fee is calculated from the work first, then turned into the proposal and the project budget, so the numbers never have to be re-typed.
Review the proposed stage, team and hours workflow in a demo and confirm how your past-project data can be used. Then check that the fee proposal and project budget reflect the agreed scope.
To price a real project with your own data, book a demo.